1.3 Status of Construction Works in the Reporting Period
2 Summary of EM&A Requirements and Mitigation Measures
2.2 Environmental Mitigation Measures
5 Environmental Non-conformance
6 Comments, Recommendations and Conclusion
Figure 1 Site Layout Plan and Monitoring Stations
C. Environmental Mitigation Measures – Implementation Status
D. Meteorological Data Extracted from Hong Kong Observatory
E. Graphical Plots of the Monitoring Results
G. Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions
This Quarterly EM&A Report presents the monitoring works at both the main works of M+ Museum and Lyric Theatre Complex conducted from 1 February 2021 to 30 April 2021. The construction works and EM&A programme for M+ Museum was completed on 28 February 2021.
The impact stage EM&A programme for the Project includes air quality, noise, water quality, waste, landscape and visual monitoring. The recommended environmental mitigation measures were implemented on site and regular inspections were carried out to ensure that the environmental conditions are acceptable.
The EM&A programme was carried out by the ET in accordance with the EM&A Manual requirements. It is concluded from the environmental monitoring and audit works that adequate environmental mitigation measures have been implemented by the contractors where appropriate in the reporting quarter.
Exceedance of Action and Limit Levels
There was no breach of Action and Limit levels for Air Quality (1-hour TSP and 24-hour TSP) and Noise in this reporting quarter.
Implementation of Mitigation Measures
Construction phase weekly site inspections were carried out to confirm the implementation measures undertaken by the Contractors in the reporting quarter. The status of implementation of mitigation measures during the reporting quarter is shown in Appendix C.
Landscape and visual impact inspections were conducted as part of the abovementioned weekly site inspections during the reporting quarter. No adverse comment on landscape and visual aspects were made during these inspections.
Record of Complaints
Three complaints were received during the reporting quarter.
Record of Notifications of Summons and Successful Prosecutions
No notifications of summons and successful prosecutions were recorded in the reporting quarter.
Mott MacDonald Hong Kong Limited (MMHK) was commissioned to undertake the Environmental Team (ET) services (including environmental monitoring and audit (EM&A)) for the construction of M+ Museum Main Works (Contract No.: CC/2015/3A/022) and Lyric Theatre Complex including the Foundation Works (Contract No.: CC/2015/3A/014), L1 Contract (Contract No. CC/2017/3A/030) and L2 Contract (Contract No. CC/2017/3A/031) at West Kowloon Cultural District (WKCD) (The Project) as part of the WKCD development. The Project Proponent is the West Kowloon Cultural District Authority (WKCDA). The construction works and EM&A programme for M+ Museum was commenced on 31 October 2015 and completed on 28 February 2021, and the construction works and EM&A programme for Lyric Theatre Complex was commenced on 1 March 2016.
The overall works for the WKCD fall under two separate categories of Designated Project (DP) of the Environmental Impact Assessment Ordinance (EIAO), namely an “engineering feasibility study of urban development projects with a study area covering more than 20 ha or involving a total population of more than 100 000” (Item 1 of Schedule 3) and “an underpass more than 100m in length under the built areas” (Item A.9, Part I, Schedule 2). An Environmental Permit No. EP-453/2013/B (EP) was issued with respect to the “Underpass Road and Austin Road Flyover Serving the West Kowloon Cultural District” which specifically includes the abovementioned category of DP under Item A.9, Part I, Schedule 2 of the EIAO. The captioned projects include part of the abovementioned underpass road located within the site boundary also falls under this same category.
The M+ museum development aims to provide an iconic presence for the M+ museum, semi-transparent vertical plane, housing education facilities, a public restaurant and museum offices. At ground and lower levels, generous access will be provided to the park and other West Kowloon Cultural District facilities, alongside a public resource centre, theatres, retail and dining, and back-of-house functions.
The 1,200-seat Lyric Theatre Complex will be Hong Kong’s first world-class facility for dance performances, including ballet, contemporary and Chinese dance forms. In the run up to the opening of further major performing arts venues in the WKCD, it will also be used for a wide variety of performing arts events including drama, opera and musical performances. The Lyric Theatre Complex will act as a platform for Hong Kong’s leading arts organisations and be a new major venue to show programmes from Asia and worldwide.
The Quarterly EM&A Report is prepared in accordance with the Clause 3.4 of the Environmental Permit No. EP-453/2013/B. This Quarterly EM&A Report presents the monitoring works conducted from 1 February 2021 to 30 April 2021. The purpose of this report is to summarise the findings in the EM&A of the project over the reporting period.
The organisation chart and lines of communication with respect to the on-site environmental management structure together with the contact information of the key personnel are shown in Appendix A.
During the reporting period, construction works at M+ Museum undertaken include:
● M+
– 2/F and B2 fit out
– 2/F MEP modification works for PPEL
– Tower UF solar panels installation
– Overall area MEP flushing out/ rectifications
– 3F landscaping works rectification
● CSF
– Defect rectifications
● WKCDA Tower
– MEP Post-OP installation
– GF paving
– Post-OP weather-tight works (indoor)
During the reporting period, construction works at L1 undertaken include:
● Excavation and lateral support works
● Extended basement structure construction
● Slab construction
● Cutting of pipe pile wall
● AET protection – Construction of at-grade Slab
● Construction of dog house
● Column installation
● Box culvert outfall to Victoria Harbour (PIW & Cofferdam B works)
● Austin Road West lay-by (PIW Works)
● Cofferdam at the M+ Museum to LTC interface on the waterfront
During the reporting period, construction works at L2 undertaken include:
● LTC construction
Structure
– Falsework and formwork erection
– Reinforcement work
– Concrete work
ABWF & MEP work
● DSC cofferdam (Cofferdam A)
– Remedial work to existing puddle flange in pump cell
– Construction of valve chamber
– Lay pipe bedding
– Install DCS pipes/valve/fitting
– Construct RC thrust blocks
● Modification to existing pump cell
– ABWF works
● Extended basement
– ABWF & MEP Work
● Vibration isolation spring system installation
– Install spring
The Construction Works Programme of the Project is provided in Appendix B. A layout plan of the Project is provided in Figure 1.
In accordance with the EM&A Manual, environmental parameters including air quality, noise, landscape and visual have been monitored. The specific parameters, monitoring frequency and the respective Action and Limit levels are given in Table 2.1. Locations of the monitoring stations are provided in Figure 1.
Table 2.1: Summary of Impact EM&A Requirements
Parameters |
Descriptions |
Locations |
Frequencies |
Action level |
Limit level |
Air Quality |
24-Hour TSP |
AM1 - International Commerce Centre |
At least once every 6 days |
143.6 μg/m3 |
260 μg/m3 |
1-Hour TSP |
AM1 - International Commerce Centre |
At least 3 times every 6 days |
273.7 μg/m3 |
500 μg/m3 |
|
24-Hour TSP |
AM2 - The Harbourside Tower 1 |
At least once every 6 days |
151.1 μg/m3 |
260 μg/m3 |
|
1-Hour TSP |
AM2 - The Harbourside Tower 1 |
At least 3 times every 6 days |
274.2 μg/m3 |
500 μg/m3 |
|
Noise |
Leq, 30 minutes |
NM1- The Harbourside Tower 1 |
Weekly |
When one documented complaint is received from any one of the sensitive receivers |
75 dB(A) |
Landscape & Visual |
Monitor implementation of proposed mitigation measures during the construction stage |
As described in Table 9.1 and 9.2 of the EM&A Manual |
Bi-weekly |
N/A |
N/A |
In the context of the monitoring activities at M+ Museum
and the Lyric Complex, three monitoring stations had been considered, including
AM1 (International Commerce Centre), AM2 (The Harbourside Tower 1) for air
monitoring, and NM1 (The Harbourside Tower
In the context
of the monitoring activities at M+ Museum and the Lyric Complex, three
monitoring stations had been considered, including AM1 (International Commerce
Centre), AM2 (The Harbourside Tower 1) for air monitoring, and NM1 (The
Harbourside Tower 1) for noise monitoring. Other monitoring locations were so
far away from M+ Museum and the Lyric Complex and could not be representative
for impact monitoring.
The Harbourside management office formally rejected our proposal of setting up air quality and noise monitoring equipment on its premises at the podium level of Tower 1 (AM2/NM1) on 10 November 2015. Nevertheless, suitable air quality monitoring location at AM2 was identified on the ground floor in front of The Harbourside Tower 1, which is at the same location as that of baseline monitoring for consistency. No management approval is required at the ground floor for conducting the air monitoring. However, the electricity supply at AM2 was suspended from 31 August 2016 and was no longer available. In order to have a more secure electricity supply, an alternative air monitoring location (AM2A) was identified at Austin Road West opposite to The Harbourside Tower 1, which is close to Lyric Theatre Complex site entrance. This alternative air monitoring location was approved by EPD on 28 September 2016. Due to works programme, the air monitoring location AM2A has been relocated to the alternative monitoring location AM2B at the 1st floor of Gammon’s site office, which was approved by EPD on 21 February 2019.
Alternative noise monitoring location was identified at The Arch (NM2); however, The Arch management office formally rejected our proposal of setting up noise monitoring equipment on its premises on 23 November 2015. On the other hand, noise monitoring at G/F of Harbourside could not be representative. However, approval from the management office of the International Commerce Centre has been granted on 29 February 2016 for conducting noise monitoring at the alternative noise monitoring location identified at the podium floor (NM1A) which is free from screening to the construction activities.
In short, 2 air quality monitoring stations and 1 noise impact monitoring station were confirmed for the impact monitoring.
Environmental mitigation measures have been recommended in the EM&A Manual. Summary of implementation status of the environmental mitigation measures is provided in Appendix C.
In accordance with the EM&A Manual, impact monitoring has been conducted in the reporting quarter. Meteorological data for the reporting quarter have been extracted from Hong Kong Observatory and presented in Appendix D. Monitoring data with graphical presentation for the reporting quarter are shown in Appendix E. A summary on the monitoring results are presented in Table 3.1.
Table 3.1: Summary of Monitoring Data
Parameter |
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|
|
|
|
1 hour TSP
|
AM1 |
19 |
67 |
38 |
AM2B |
30 |
91 |
56 |
|
24 hour TSP
|
AM1 |
13 |
113 |
35 |
AM2B |
17 |
101 |
59 |
|
Construction Noise |
|
|
|
|
Leq(30min) |
NM1A |
67 |
69 |
68 |
Summary of the exceedances in the reporting quarter is tabulated in Table 3.2.
Table 3.2: Summary of Exceedances
Monitoring Station |
Parameter |
No. of Exceedance |
Action Taken |
|
|
|
|||
|
|
Action Level |
Limit Level |
|
Air Quality |
|
|
|
|
AM1 |
1 hour TSP |
0 |
0 |
N/A |
24 hour TSP |
0 |
0 |
N/A |
|
AM2B |
1 hour TSP |
0 |
0 |
N/A |
24 hour TSP |
0 |
0 |
N/A |
|
Construction Noise |
|
|
|
|
NM1A |
Leq(30min) |
0 |
0 |
N/A |
All 1-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance was recorded.
All 24-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance was recorded.
All construction noise monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance was recorded.
All landscape and visual impact inspections were conducted as scheduled in the reporting quarter. No adverse comment on landscape and visual aspects were recorded.
As advised by the Contractor, 0.0 tonne, 0.0 tonne and 0.0 tonne of inert C&D material was disposed of as public fill to Chai Wan Public Fill Barging Point, Tuen Mun Area 38 and Tseung Kwan O Area 137 Public Fill respectively in the reporting quarter, while 118.0 tonnes of general refuse were disposed of at SENT landfill. 0.0 tonne of metals, 0.0 tonne of paper/cardboard packaging, 0.0 tonne of plastic and 0.0 tonne of timber was collected by recycling contractors in the reporting quarter. 0.0 tonne of inert C&D materials was reused on site. 0.0 tonne of inert C&D materials was reused in other projects and 0.0 tonne of inert C&D materials was disposed to sorting facility. 0.0 tonne of chemical wastes was collected by licensed contractors in the reporting quarter.
The actual amounts of different types of waste generated by the activities of construction works at M+ Museum in the reporting quarter are shown in Appendix F.
As advised by the Contractor (L1 and L2 Contract), 1033.29 tonnes, 550.44 tonnes and 0.00 tonne of inert C&D material were disposed of as public fill to Tseung Kwan O Area 137, Tuen Mun Area 38, and Chai Wan Public Fill Barging Point respectively in the reporting quarter, while 1999.4 tonnes of general refuse were disposed of at SENT and WENT landfill. 986.1 tonnes of metals, 0.6 tonnes of paper/cardboard packaging, 0.0 tonne of plastic and 0.0 tonne of timber were collected by recycling contractors in the reporting quarter. 0.0 tonne of inert C&D materials was reused on site. 0.0 tonne of fill materials was imported for use at site and 0.0 tonne of inert C&D materials was reused in other projects. 0.0 tonne of inert C&D materials was disposed to sorting facility and 0.0 tonne of chemical wastes was collected by licensed contractors in the reporting quarter.
The actual amounts of different types of waste generated by the activities of construction works at Lyric Theatre Complex in the reporting quarter are shown in Appendix F.
Three complaints were received in the reporting quarter. No notifications of summons and successful prosecutions were received in the reporting quarter.
The first complaint was referred by EPD from nearby resident about the noise from WKCD site on 28 March 2021. The resident reflected that the construction site area of WKCD next to the West Kowloon Station produces annoying noise every morning, and there is a piling rig operating every morning which possibly produces the concerned noise. The investigation revealed that the complaint was not related to M+ Museum and Lyric Theatre Complex, as the construction works for M+ Museum were ended in February 2021 and both M+ Museum and Lyric Theatre Complex were far away from the concerned area. Also, there were no piling works on Lyric complex sites. Hence the complaint could be attributable to M+ Museum and Lyric Theatre Complex. However, noise mitigation measures will continue to be strictly implemented on site. Nevertheless, the contractors are reminded to strengthen the implementation of the recommended noise mitigation measures to reduce impacts to nearby residents.
The second complaint was received on 12 April 2021, West Kowloon Cultural District Authority (WKCDA) has received a complaint case referred by Home Affairs Bureau (HAB) on the noise disturbance at WKCD construction site. The complainant claimed that construction noise was heard at the construction site close to Xiqu Centre after 20:00. As the complainant specified that the noise was from the construction site next to Xiqu Centre, and Lyric Theatre Complex was far away from the concerned area, hence the complaint could not be attributable to Lyric Theatre Complex. However, noise mitigation measures will continue to be strictly implemented on site to reduce impacts to nearby residents.
The third complaint was referred by EPD. On 18 April 2021, EPD has received a complaint from a resident of The Arch relating to WKCD construction site activities. According to email sent by EPD on 20 April 2021, the complainant claimed that there was a noise from construction site of Zone 2A, including the engine of lorry after 00:00 on 15 and 16 April 2021. As the complainant specified that the noise was from construction site of Zone 2A, and Lyric Theatre Complex was far away from the concerned area, hence the complaint could not be attributable to Lyric Theatre Complex. However, noise mitigation measures will continue to be strictly implemented on site to reduce impacts to nearby residents.
The cumulative statistics on complaints, notifications of summons and successful prosecutions were provided in Appendix G.
Based on the observations made during site audits, landscape inspections, and construction dust and noise monitoring results, no non-compliances and exceedances of air quality and noise were recorded in the reporting quarter.
Reviewing the implementation of the recommended mitigation measures in the EM&A Manual, it was observed that they were effective and efficient in controlling the potential impacts due to construction of the project during the reporting period. Review of the effectiveness and efficiency of the EM&A programme will continue, and recommendations will be provided to remediate any potential impacts due to the project and to improve the EM&A programme if deficiencies of the existing EM&A programme are identified.
The EM&A programme as recommended in the EM&A Manual has been undertaken. The construction works of M+ Museum main works commenced on 31 October 2015 and completed on 28 February 2021; and the construction of Lyric Theatre Complex commenced on 1 March 2016.
Monitoring of air quality and noise with respect to the Project is underway. In particular, the 1-hour TSP, 24-hour TSP and noise level (as Leq, 30 minutes) under monitoring have been checked against established Action and Limit levels. There was no breach of Action and Limit levels for Air Quality (1-hour TSP and 24-hour TSP) and Noise in this reporting quarter.
Three complaints were received in the reporting quarter. No notifications of summons and successful prosecutions were received during the reporting quarter.
Weekly construction phase site inspections and bi-weekly landscape and visual impact inspections were conducted during the reporting quarter as required. It was observed that the Contractor had implemented all possible and feasible mitigation measures to mitigate the potential environmental impacts during construction phase works.