Contents

Executive summary

1       Introduction

1.1      Background

1.2      Project Organisation

1.3      Environmental Status in the Reporting Period

2       Summary of EM&A Requirements and Mitigation Measures

2.1      Monitoring Requirements

2.2      Environmental Mitigation Measures

3       Summary of EM&A Results

3.1      Monitoring Data

3.2      Monitoring Exceedances

3.2.1         1-hour TSP Monitoring

3.2.2         24-hour TSP Monitoring

3.2.3         Construction Noise Monitoring

3.2.4         Landscape and Visual Monitoring

4       Waste Management

4.1      Zone 2A

4.2      Zone 2B & 2C

5       Environmental Non-conformance

6       Comments, Recommendations and Conclusion

6.1      Comments

6.2      Recommendations

6.3      Conclusion

Figure 1      Site Layout Plan and Monitoring Stations

Appendices

A.      Project Organisation

B.      Construction Programme

C.      Environmental Mitigation Measures – Implementation Status

D.      Meteorological Data Extracted from Hong Kong Observatory

E.      Graphical Plots of the Monitoring Results

F.      Waste Flow table

G.      Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions

 

  


Executive summary

This Quarterly EM&A Report presents the monitoring works conducted at Zone 2A and Zone 2B & 2C from 1 May 2022 to 31 July 2022.

The impact stage EM&A programme for the Project includes air quality, noise, water quality, waste, landscape and visual monitoring. The recommended environmental mitigation measures were implemented on site and regular inspections were carried out to ensure that the environmental conditions are acceptable.

The EM&A programme was carried out by the ET in accordance with the EM&A Manual requirements. It is concluded from the environmental monitoring and audit works that adequate environmental mitigation measures have been implemented by the contractors where appropriate in the reporting quarter.

Exceedance of Action and Limit Levels

There was no breach of Action or Limit Levels for Air Quality (1-hour TSP and 24-hour TSP) and Construction Noise in the reporting quarter.

Implementation of Mitigation Measures

Construction phase weekly site inspections were carried out to confirm the implementation measures undertaken by the Contractors in the reporting quarter. The status of implementation of mitigation measures during the reporting quarter is shown in Appendix C.

Landscape and visual impact inspections were conducted as part of the above-mentioned weekly site inspections during the reporting quarter. No adverse comment on landscape and visual aspects were made during these inspections.

Record of Complaints

Seven environmental complaints were received during the reporting quarter.

Record of Notifications of Summons and Successful Prosecutions

No notifications of summons and successful prosecutions were recorded in the reporting quarter.

 

 

 

1        Introduction

1.1             Background

Apex Testing & Certification Limited (Apex) was commissioned to undertake the Environmental Team (ET) services (including environmental monitoring and audit (EM&A)) for the construction activities in Zone 2A, consisting of Foundation, Excavation and Lateral Support Works for Integrated Basement and Underground Road (Contract No.: GW/2020/05/073) ; and Zone 2B & 2C consisting of Piling Works for Integrated Basement and Underground Road (Contract No.: CC/2020/2B/088) at WKCD. The major construction works and EM&A programme for Zone 2A and Zone 2B & 2C commenced on 3 October 2020 and 30 September 2021 respectively.

The overall works for the WKCD fall under two separate categories of Designated Project (DP) of the Environmental Impact Assessment Ordinance (EIAO), namely an “engineering feasibility study of urban development projects with a study area covering more than 20 ha or involving a total population of more than 100 000” (Item 1 of Schedule 3) and “an underpass more than 100m in length under the built areas” (Item A.9, Part I, Schedule 2). An Environmental Permit No. EP-453/2013/B (EP) was issued with respect to the “Underpass Road and Austin Road Flyover Serving the West Kowloon Cultural District” which specifically includes the abovementioned category of DP under Item A.9, Part I, Schedule 2 of the EIAO. The captioned projects include part of the abovementioned underpass road located within the site boundary falls under this same category.

The purpose of the development in Zone 2A and Zone 2B & 2C is to reserve for Integrated Basement (IB) and Underground Road (UR). The Zone 2A construction activities involve the foundation, excavation and lateral support (ELS) works, road works, drainage diversion works, and temporary car parking. The Zone 2B & 2C construction activities involve the piling works.

The Quarterly EM&A Report is prepared in accordance with the Clause 3.4 of the Environmental Permit No. EP-453/2013/B. This Quarterly EM&A Report presents the monitoring works at Zone 2A and Zone 2B & 2C from 1 May 2022 to 31 July 2022. The purpose of this report is to summarise the findings in the EM&A of the project over the reporting period.

1.2             Project Organisation

The organisation chart and lines of communication with respect to the on-site environmental management structure together with the contact information of the key personnel are shown in Appendix A.

1.3             Environmental Status in the Reporting Period

During the reporting period, construction works at Zone 2A undertaken include:

Zone 2A-1

    ELS (Stage 1) – Grouting / Pipe Pile Works

    King Post & Erection of Steel Column for Working Platform

    Stage 2 Grouting

    Pumping Test

    Installation of Pump Wells

Zone 2A-2

    ELS (Stage 1) – Grouting / Pipe Pile Works

    King Post & Erection of Steel Column for Working Platform

    Pipe Pile Construction

    Stage 2 Grouting

    Pumping Test

    Installation of Pump Wells

    Pumping Test

 

During the reporting period, construction works at Zone 2B & 2C undertaken include:

KD01 (Stage 1-1), KD03 (Stage 3-1)

    Bored Pile Works

    RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation

KD02 (Stage 5-1)

    Bored Pile Works

    Airlifting, Cage Installation & Concreting

KD04 (Stage 4-1)

    Bored Pile Works

    RCD Drilling and Excavation

KD05 (Section 1), KD06 (Section 2)

    Predrilling

    Bored Pile Works

    RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation

KD07 (Section 3)

    Predrilling

    Trial Pile Works

    Airlifting, Cage Installation & Concreting

    Bored Pile Works

    RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation

KD08 (Section 4)

    Bored Pile Works

    RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation

    Socketed Steel H Piling

KD09 (Section 5)

    Predrilling

    Bored Pile Works

    RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation

    Socketed Steel H Piling

The Construction Works Programme of the Project is provided in Appendix B. A layout plan of the Project is provided in Figure 1.

 

 

 

2        Summary of EM&A Requirements and Mitigation Measures

2.1             Monitoring Requirements

In accordance with the EM&A Manual, environmental parameters including air quality, noise, landscape and visual have been monitored. The specific parameters, monitoring frequency and the respective Action and Limit Levels are given in Table 2.1. Locations of the monitoring stations are provided in Figure 1.

Table 2.1:         Summary of Impact EM&A Requirements

Parameters

Descriptions

Locations

Frequencies

Action Level

Limit Level

Air Quality

24-Hour TSP

AM3 - The Victoria Towers Tower 1

At least once every 6 days

152.4 μg/m3

260 μg/m3

1-Hour TSP

AM3 - The Victoria Towers Tower 1

At least 3 times every 6 days

280.4 μg/m3

500 μg/m3

24-Hour TSP

AM4 - Canton Road Government Primary School

At least once every 6 days

152.6 μg/m3

260 μg/m3

1-Hour TSP

AM4 - Canton Road Government Primary School

At least 3 times every 6 days

278.5 μg/m3

500 μg/m3

24-Hour TSP

AM5 - Topside Developments at West Kowloon Terminus Site

At least once every 6 days

141.1 μg/m3

260 μg/m3

1-Hour TSP

AM5 - Topside Developments at West Kowloon Terminus Site

At least 3 times every 6 days

275.4 μg/m3

500 μg/m3

Noise

Leq, 30 minutes

NM2 - The Arch, Sun Tower

Weekly

When one documented complaint is received from any one of the sensitive receivers

75 dB(A)

Leq, 30 minutes

NM3 - The Victoria Towers Tower 1

Weekly

When one documented complaint is received from any one of the sensitive receivers

75 dB(A)

Leq, 30 minutes

NM4 - Canton Road Government Primary School

Weekly

When one documented complaint is received from any one of the sensitive receivers

70/65 dB(A)^

Leq, 30 minutes

NM5 -Development next to Austin Station

Weekly

When one documented complaint is received from any one of the sensitive receivers

75 dB(A)

Landscape & Visual

Monitor implementation of proposed mitigation measures during the construction stage

As described in Table 9.1 and 9.2 of the EM&A Manual

Bi-weekly

N/A

N/A

Note:

^70 dB(A) for schools and 65 dB(A) during school examination periods.

The EM&A programme for the Project require 5 air monitoring stations and 5 noise quality monitoring stations located closest to the Project area. With regard to the monitoring activities at M+ Museum and the Lyric Complex, three monitoring stations had been considered, including AM1, AM2 for air monitoring, and NM1 for noise monitoring. In the context of the construction activities in Zone 2A and Zone 2B & 2C, all other monitoring locations including AM3, AM4, and AM5 for air monitoring; and NM2, NM3, NM4 and NM5 for noise monitoring, have been taken into account. However, access to all these originally designated monitoring stations was declined. Therefore, alternative monitoring stations was identified and proposed. 

With regard to air monitoring, alternative monitoring locations (AM3A, AM4A, and AM5A) were identified at ground floor at the Northeast corner of West Kowloon Station’s station box, at ground floor at the Southeast corner of West Kowloon Station’s station box, and at ground floor at the North of West Kowloon Station’s station box respectively. AM3A, AM4A, and AM5A were set in same direction to the area of major construction site activities in Zone 2A0. These alternative air monitoring locations (AM3A, AM4A, and AM5A) were approved by EPD on 29 September 2020. 

For noise monitoring, alternative noise monitoring location (NM2A) was identified at the ground floor in front of The Arch - Sun Tower, which is at the same location as stated in the EM&A Manual for consistency. This alternative noise monitoring location was approved by EPD on 29 September 2020. Other alternative noise monitoring locations (NM3A, NM4A, and NM5A) were identified at the ground floor in front of the Xiqu Centre, at the ground floor next to Tsim Sha Tsui Fire Station, and at the Pedestrian road (ground floor) outside West Kowloon Station respectively. NM3A, NM4A and NM5A were set closer to the construction site boundary with more direct line sight to the major site activities and higher exposure to the construction noise with no disturbance to the premises’ occupants during noise monitoring activities. These alternative noise monitoring locations (NM3A, NM4A, and NM5A) were approved by EPD on 29 September 2020.

Therefore, 3 air quality monitoring stations and 4 noise impact monitoring station were confirmed for the impact monitoring for construction activities in Zone 2A and Zone 2B & 2C.

2.2             Environmental Mitigation Measures

Environmental mitigation measures have been recommended in the EM&A Manual. Summary of implementation status of the environmental mitigation measures is provided in Appendix C.

 

 

 

3        Summary of EM&A Results

3.1             Monitoring Data

In accordance with the EM&A Manual, impact monitoring has been conducted in the reporting quarter. Meteorological data for the reporting quarter have been extracted from Hong Kong Observatory and presented in Appendix D. Monitoring data with graphical presentation for the reporting quarter are shown in Appendix E. A summary on the monitoring results are presented in Table 3.1.

Table 3.1:         Summary of Monitoring Data

Parameter

Monitoring Location

Minimum

Maximum

Average

Air Quality

 

 

 

 

1 hour TSP

AM3A

31

64

47

1 hour TSP

AM4A

31

68

47

1 hour TSP

AM5A

33

67

47

24 hour TSP

AM3A

32

60

45

24 hour TSP

AM4A

31

62

45

24 hour TSP

AM5A

35

68

46

Construction Noise

 

 

 

 

Leq(30min)

NM2A

60

62

62

Leq(30min)

NM3A

60

65

65

Leq(30min)

NM4A

60

64

64

Leq(30min)

NM5A

63

65

64

3.2             Monitoring Exceedances

Summary of the exceedances in the reporting quarter is tabulated in Table 3.2.

Table 3.2:         Summary of Exceedances

Monitoring Station

Parameter

No. of Exceedance

Action Taken

Action Level

Limit Level

Air Quality

 

 

 

 

AM3A

1 hour TSP

0

0

N/A

24 hour TSP

0

0

N/A

AM4A

1 hour TSP

0

0

N/A

24 hour TSP

0

0

N/A

AM5A

1 hour TSP

0

0

N/A

24 hour TSP

0

0

N/A

Construction Noise

 

 

 

 

NM2A

Leq(30min)

0

0

N/A

NM3A

Leq(30min)

0

0

N/A

NM4A

Leq(30min)

0

0

N/A

NM5A

Leq(30min)

0

0

N/A

3.2.1         1-hour TSP Monitoring

All 1-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of 1-hour TSP for Air Quality was recorded.

3.2.2         24-hour TSP Monitoring

All 24-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of 24-hour TSP for Air Quality was recorded.

3.2.3         Construction Noise Monitoring

All construction noise monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of Noise was recorded in the reporting quarter.

3.2.4         Landscape and Visual Monitoring

All landscape and visual impact inspections were conducted as scheduled in the reporting quarter. No adverse comment on landscape and visual aspects were recorded.

 

 

 

4        Waste Management

4.1        Zone 2A

As advised by the Contractor, 156.88 tonnes, 694.25 tonnes of inert C&D material were disposed of as public fill to Tseung Kwan O Area 137 Public Fill, and Tuen Mun Area 38 respectively in the reporting quarter, while 25.64 tonnes of general refuse were disposed of at SENT landfill. 0.0 tonne of metals, 0.0 tonne of paper/cardboard packaging, 0.0 tonne of plastic and 0.0 tonne of timber were collected by recycling contractors in the reporting quarter. 0.0 tonne of inert C&D materials were reused on site. 0.0 tonne of fill materials were imported for use at site and 0.0 tonne of inert C&D materials was reused in other projects. 0.0 tonne of inert C&D materials was disposed to sorting facility and 0.0 tonne of chemical wastes was collected by licensed contractors in the reporting quarter.

4.2        Zone 2B & 2C

As advised by the Zone 2B & 2C Contractor, 29543.96 tonnes and 16647.81 tonnes of inert C&D material were disposed of at Tuen Mun Area 38 and Tseung Kwan O Area 137 Public Fill in the reporting quarter, while 46.58 tonnes of general refuse were disposed of at SENT landfill. 0.0 tonne of metals, 0.0 tonne of paper/cardboard packaging, 0.0 tonne of plastics and 0.0 tonne of timber was collected by recycling contractors in the reporting quarter. 9706.37 tonnes of inert C&D material were reused on site. 0.0 tonne of inert C&D material was imported for reuse at site and 39982.35 tonne of inert C&D material were reused in other projects. 0.0 tonne of inert C&D material was disposed to sorting facility and 0.0 tonne of chemical waste was collected by licensed contractors in the reporting quarter.

The actual amounts of different types of waste generated by the activities of construction works at Zone 2A and Zone 2B & 2C in the reporting quarter are shown in Appendix F.

 

 

 

5        Environmental Non-conformance

There was no breach of Action or Limit Levels for Air Quality (1-hour TSP and 24-hour TSP) and Construction Noise in the reporting quarter.

Seven complaints were received in the reporting quarter. Three complaints in June and four complaints in July. No notifications of summons and successful prosecutions were received in the reporting quarter.

On 27 June 2022, EPD has received a complaint regarding muddy water discharge at WKCD construction site and the complaint was referred by EPD on the same day. The complainant (a resident of the Harbourside) claimed that water from WKCD construction site was observed to be continuously discharged into the sea. Investigation revealed that no construction work was undertaken by WKCD Zone 2A site and no abnormalities were found at the seafront of Victoria Harbour on Zone 2A site on 27 June 2022. Besides, no water and site runoff discharge was observed on Zone 2B & 2C site on 27 June 2022. In addition, existing mitigation measures have been properly maintained on site. Thereby, the complaint might not attributable to Zone 2 sites. Nonetheless, the Contractor is recommended to strictly maintain good site practices to avoid water pollution to the waterbody of Victoria Harbour.

On 29 June 2022, EPD has received a complaint from a district councilor regarding polluted water discharge at WKCD construction site. The complaint was referred by EPD on the same day. According to the video taken by the complainant (a resident of Kowloon Station), the complainant claimed that white bubble discharge was observed which contaminated the harbour at around 6:48am. Investigation revealed that no construction work was undertaken by WKCD Zone 2 sites on 29 June 2022. Moreover, as from the video provided by the complainant, the location of discharge was outside WKCD Zone 2 sites boundary. Thereby, the complaint might not attributable to Zone 2 sites. Nonetheless, the Contractor is recommended to strictly maintain good site practices to avoid water pollution to the waterbody of Victoria Harbour.

On 30 June 2022, EPD has received a follow-up complaint from a district councilor regarding polluted water discharge at WKCD construction site. The complaint was referred by EPD on the same day. The complainant (a resident of Kowloon Station) claimed that white bubble discharge was observed at 6:40am and he also claimed that some white bubble even floated to the sea near the Harbour City. The complainant had also provided videos demonstrating the concerned water pollution. Investigation revealed that no construction work was undertaken by WKCD Zone 2 sites on 30 June 2022. Moreover, as from the video provided by the complainant, the location of discharge was outside WKCD Zone 2 sites boundary. Thereby, the complaint might not attributable to Zone 2 sites. Nonetheless, the Contractor is recommended to strictly maintain good site practices to avoid water pollution to the waterbody of Victoria Harbour.

On 15 July 2022, WKCDA has received a complaint referred by the EPD regarding construction dust pollution generated from WKCD construction site. On 15 July 2022, the complainant claimed that air pollution arose from a large construction site nearby the Museum Drive, so that the sand scratched the glass of the vehicles when the residents from The Arch were driving by. The complainant also mentioned that the construction site consisted of a joint venture of various engineering companies. According to the description provided by the complainant, the concerned air pollution issue on 15 July 2022 was not related to WKCD Zone 2A site. However, some sand on the nearby public road might be possibly related to Zone 2B & 2C site activities. Thereby, the concerned sand on the public road might be attributable to Zone 2B & 2C site activities. In response, prompt actions have been taken by the Contractor to clean the public road and strengthen the dust control measures on site. In the meantime, existing mitigation measures (dust suppression measures, regular cleaning on the public road, wheel washing facility) have been implemented and properly maintained on Zone 2B & 2C site to avoid nuisance to the public. Dust monitoring is also regularly conducted at the site boundary with no exceedance. Nonetheless, the Contractors are recommended to maintain good practice on site, and strengthen the implementation of dust control measures to reduce impacts to the nearby neighbors.

On 22 July 2022, WKCDA has received a complaint referred by the EPD regarding polluted water discharge from WKCD construction site to the public road. The complainant claimed that "地盤污水流出街 圓方溜冰場對出柯士甸道西西九文化區地盤" (Polluted water flowed out to the street from the WKCD construction site which located at the opposite side to the Element ice rink.). Investigation at Zone 2A site revealed that the concerned location was not within the site boundary of Zone 2A site. Thereby, the complaint might not be attributable to the Zone 2A site. Nevertheless, the Contractor is recommended to strengthen water pollution mitigation measures on site to reduce impacts to the public. Investigation at Zone 2B & 2C site revealed that the concerned water might possibly due to the water runoff from the vehicles after wheel washing when leaving the captioned site vehicular gate. The Contractor has been reminded to strengthen public road cleaning to minimise impacts to the public.

On 26 July 2022, the EPD has received a complaint from a public regarding polluted water discharge at WKCD construction site and referred the case on the same day. The complainant claimed that "投訴在藝術公園隔離地盤於下午排放污水" (Polluted water discharged from the  construction site next to the Art Park in the afternoon). Investigation at Zone 2A site revealed that the concerned location was not within the site boundary of Zone 2A site. Thereby, the complaint might not be attributable to the Zone 2A site. Nevertheless, the Contractor is recommended to strictly maintain good site practices to avoid polluted water flowing into the nearby waterbody.  Investigation at Zone 2B & 2C site revealed that the complaint might not be attributable to WKCD Zone 2B & 2C site. However, the Contractor has been reminded to strictly implement and maintain good site practices to avoid water pollution to the nearby waterbody.

On 26 July 2022, the EPD has also received a complaint from a public regarding polluted water discharge at WKCD construction site and referred the case on the same day. The complainant claimed that " M+ 藝術館旁邊的地盤非法排放污水" (Illegal discharge of polluted water from the construction site next to the M+ museum). Investigation at Zone 2A site revealed that the concerned location was not within the site boundary of Zone 2A site. Thereby, the complaint might not be attributable to the Zone 2A site. Nevertheless, the Contractor is recommended to strictly maintain good site practices to avoid polluted water flowing into the waterbody of Victoria Harbour. Investigation at Zone 2B & 2C site revealed that the complaint might not be attributable to WKCD Zone 2B & 2C site. However, the Contractor has been reminded to strictly implement and maintain good site practices to avoid water pollution to the nearby waterbody.

The cumulative statistics on complaints, notifications of summons and successful prosecutions were provided in Appendix G.

 

 

 

6        Comments, Recommendations and Conclusion

6.1             Comments

Based on the observations made during site audits and landscape inspections, and construction dust and noise monitoring results, no non-compliances and exceedances of air quality and construction noise were recorded in the reporting quarter.

6.2             Recommendations

Reviewing the implementation of the recommended mitigation measures in the EM&A Manual, it was observed that they were effective and efficient in controlling the potential impacts due to construction of the project during the reporting period. Review of the effectiveness and efficiency of the EM&A programme will continue, and recommendations will be provided to remediate any potential impacts due to the project and to improve the EM&A programme if deficiencies of the existing EM&A programme are identified.

6.3             Conclusion

The EM&A programme as recommended in the EM&A Manual has been undertaken since the construction works of Zone 2A and Zone 2B & 2C commenced on 3 October 2020 and 30 September 2021 respectively.

Monitoring of air quality and noise with respect to the Project is underway. In particular, the 1-hour TSP, 24-hour TSP and noise level (as Leq, 30 minutes) under monitoring have been checked against established Action and Limit Levels. There was no breach of Action and Limit Levels for Air Quality (1-hour TSP and 24-hour TSP) and Construction Noise in this reporting quarter.

Seven complaints were received in the reporting quarter. No notifications of summons and successful prosecutions were received during the reporting quarter.

Weekly construction phase site inspections and bi-weekly landscape and visual impact inspections were conducted during the reporting quarter as required. It was observed that the Contractor had implemented all possible and feasible mitigation measures to mitigate the potential environmental impacts during construction phase works.