Contents
1.3 Status of Construction Works in the Reporting Period
2 Summary of EM&A Requirements and Mitigation Measures
2.2 Environmental Mitigation Measures
5 Environmental Non-conformance
6 Comments, Recommendations and Conclusion
Figure 1 Site Layout Plan and Monitoring Stations
C. Environmental Mitigation Measures – Implementation Status
D. Meteorological Data Extracted from Hong Kong Observatory
E. Graphical Plots of the Monitoring Results
G. Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions
This Quarterly EM&A Report presents the monitoring works at Lyric Theatre Complex conducted from 1 August 2021 to 31 October 2021.The construction works and EM&A programme for M+ Museum was commenced on 31 October 2015 and completed on 28 February 2021; while the construction works and EM&A programme for Lyric Theatre Complex (L1 and L2 Contracts) was commenced on 1 March 2016, and the EM&A programme for L1 Contract was completed on 30 June 2021.
The impact stage EM&A programme for the Project includes air quality, noise, water quality, waste, landscape and visual monitoring. The recommended environmental mitigation measures were implemented on site and regular inspections were carried out to ensure that the environmental conditions are acceptable.
The EM&A programme was carried out by the ET in accordance with the EM&A Manual requirements. It is concluded from the environmental monitoring and audit works that adequate environmental mitigation measures have been implemented by the contractors where appropriate in the reporting quarter.
Exceedance of Action and Limit Levels
There was no breach of Action and Limit levels for Air Quality (1-hour TSP and 24-hour TSP) and Noise in this reporting quarter.
Implementation of Mitigation Measures
Construction phase weekly site inspections were carried out to confirm the implementation measures undertaken by the Contractors in the reporting quarter. The status of implementation of mitigation measures during the reporting quarter is shown in Appendix C.
Landscape and visual impact inspections were conducted as part of the abovementioned weekly site inspections during the reporting quarter. No adverse comment on landscape and visual aspects were made during these inspections.
Record of Complaints
Six complaints were received during the reporting quarter.
Record of Notifications of Summons and Successful Prosecutions
No notifications of summons and successful prosecutions were recorded in the reporting quarter.
Mott MacDonald Hong Kong Limited (MMHK) was commissioned to undertake the Environmental Team (ET) services (including environmental monitoring and audit (EM&A)) for the construction of M+ Museum Main Works (Contract No.: CC/2015/3A/022) and Lyric Theatre Complex including the Foundation Works (Contract No.: CC/2015/3A/014), L1 Contract (Contract No. CC/2017/3A/030) and L2 Contract (Contract No. CC/2017/3A/031) at West Kowloon Cultural District (WKCD) (The Project) as part of the WKCD development. The Project Proponent is the West Kowloon Cultural District Authority (WKCDA). The construction works and EM&A programme for M+ Museum was commenced on 31 October 2015 and completed on 28 February 2021; while the construction works and EM&A programme for Lyric Theatre Complex (L1 and L2 Contracts) was commenced on 1 March 2016, and the EM&A programme for L1 Contract was completed on 30 June 2021.
The overall works for the WKCD fall under two separate categories of Designated Project (DP) of the Environmental Impact Assessment Ordinance (EIAO), namely an “engineering feasibility study of urban development projects with a study area covering more than 20 ha or involving a total population of more than 100 000” (Item 1 of Schedule 3) and “an underpass more than 100m in length under the built areas” (Item A.9, Part I, Schedule 2). An Environmental Permit No. EP-453/2013/B (EP) was issued with respect to the “Underpass Road and Austin Road Flyover Serving the West Kowloon Cultural District” which specifically includes the abovementioned category of DP under Item A.9, Part I, Schedule 2 of the EIAO. The captioned projects include part of the abovementioned underpass road located within the site boundary also falls under this same category.
The M+ museum development aims to provide an iconic presence for the M+ museum, semi-transparent vertical plane, housing education facilities, a public restaurant and museum offices. At ground and lower levels, generous access will be provided to the park and other West Kowloon Cultural District facilities, alongside a public resource centre, theatres, retail and dining, and back-of-house functions.
The 1,200-seat Lyric Theatre Complex will be Hong Kong’s first world-class facility for dance performances, including ballet, contemporary and Chinese dance forms. In the run up to the opening of further major performing arts venues in the WKCD, it will also be used for a wide variety of performing arts events including drama, opera and musical performances. The Lyric Theatre Complex will act as a platform for Hong Kong’s leading arts organisations and be a new major venue to show programmes from Asia and worldwide.
The Quarterly EM&A Report is prepared in accordance with the Clause 3.4 of the Environmental Permit No. EP-453/2013/B. This Quarterly EM&A Report presents the monitoring works conducted from 1 August 2021 to 31 October 2021. The purpose of this report is to summarise the findings in the EM&A of the project over the reporting period.
The organisation chart and lines of communication with respect to the on-site environmental management structure together with the contact information of the key personnel are shown in Appendix A.
During the reporting period, construction works at L2 undertaken include:
● LTC construction
Structure (Slab, wall, columns and beam)
– Falsework and formwork erection
– Reinforcement work
– Concrete work
ABWF & MEP work
LT temporary deck
● ASDA and Lyric Theatre Promenade
– Structure and BS works
● DSC cofferdam (Cofferdam A)
– Install DCS pipes/valve/ fittings (DN500/ DN1400) outside chamber Construction of Valve Chamber
– Construction of valve chamber (upper and middle portion)
– DCS related works
● Modification to existing pump cell
– ABWF works
● Extended basement
– ABWF & MEP work
– RC Water Tank
– RC Duct Slab (Forms/Rebar/Concrete)
– Carpark area plaster and paint
● Underpass and Associated Area
– RC Structure (Waffle Ceiling)
– ABWF & MEP work
● M+ Day 2 Works
– Hoarding Work
– Open excavation
● P32 Interim Development
– Structure works (Scaffold/forms/rebar concrete)
The Construction Works Programme of the Project is provided in Appendix B. A layout plan of the Project is provided in Figure 1.
In accordance with the EM&A Manual, environmental parameters including air quality, noise, landscape and visual have been monitored. The specific parameters, monitoring frequency and the respective Action and Limit levels are given in Table 2.1. Locations of the monitoring stations are provided in Figure 1.
Table 2.1: Summary of Impact EM&A Requirements
Parameters |
Descriptions |
Locations |
Frequencies |
Action level |
Limit level |
Air Quality |
24-Hour TSP |
AM1 - International Commerce Centre |
At least once every 6 days |
143.6 μg/m3 |
260 μg/m3 |
1-Hour TSP |
AM1 - International Commerce Centre |
At least 3 times every 6 days |
273.7 μg/m3 |
500 μg/m3 |
|
24-Hour TSP |
AM2 - The Harbourside Tower 1 |
At least once every 6 days |
151.1 μg/m3 |
260 μg/m3 |
|
1-Hour TSP |
AM2 - The Harbourside Tower 1 |
At least 3 times every 6 days |
274.2 μg/m3 |
500 μg/m3 |
|
Noise |
Leq, 30 minutes |
NM1- The Harbourside Tower 1 |
Weekly |
When one documented complaint is received from any one of the sensitive receivers |
75 dB(A) |
Landscape & Visual |
Monitor implementation of proposed mitigation measures during the construction stage |
As described in Table 9.1 and 9.2 of the EM&A Manual |
Bi-weekly |
N/A |
N/A |
In the context of the monitoring activities at M+ Museum and the Lyric Complex, three monitoring stations had been considered, including AM1 (International Commerce Centre), AM2 (The Harbourside Tower 1) for air monitoring, and NM1 (The Harbourside Tower 1) for noise monitoring. Other monitoring locations were so far away from M+ Museum and the Lyric Complex and could not be representative for impact monitoring.
The Harbourside management office formally rejected our proposal of setting up air quality and noise monitoring equipment on its premises at the podium level of Tower 1 (AM2/NM1) on 10 November 2015. Nevertheless, a suitable air quality monitoring location at AM2 was identified on the ground floor in front of The Harbourside Tower 1, which is at the same location as that of baseline monitoring for consistency. No management approval is required on the ground floor for conducting the air monitoring. However, the electricity supply at AM2 was suspended from 31 August 2016. In order to have a more secure electricity supply, an alternative air monitoring location (AM2A) was identified at Austin Road West opposite to The Harbourside Tower 1, which is close to Lyric Theatre Complex site entrance. This alternative air monitoring location was approved by EPD on 28 September 2016. Due to the works programme, the air monitoring location AM2A has been relocated to the alternative monitoring location AM2B at the 1st floor of Gammon’s site office, which was approved by EPD on 21 February 2019. In view of the upcoming construction works to be undertaken at the air monitoring station AM2B, AM2B was no longer available for conducting the impact air quality monitoring. Hence, an alternative air monitoring location was identified on the ground floor in front of The Harbourside Tower 1 (AM2) which is at the same location as the baseline monitoring and this previously approved monitoring location had also been used for the EM&A Programme from November 2015 to August 2016, the relocation was approved by EPD on 27 May 2021.
Alternative noise monitoring location was identified at The Arch (NM2); however, The Arch management office formally rejected our proposal of setting up noise monitoring equipment on its premises on 23 November 2015. On the other hand, noise monitoring at G/F of Harbourside could not be representative. However, approval from the management office of the International Commerce Centre has been granted on 29 February 2016 for conducting noise monitoring at the alternative noise monitoring location identified at the podium floor (NM1A) which is free from screening to the construction activities.
In short, 2 air quality monitoring stations and 1 noise impact monitoring station were confirmed for the impact monitoring.
Environmental mitigation measures have been recommended in the EM&A Manual. Summary of implementation status of the environmental mitigation measures is provided in Appendix C.
In accordance with the EM&A Manual, impact monitoring has been conducted in the reporting quarter. Meteorological data for the reporting quarter have been extracted from Hong Kong Observatory and presented in Appendix D. Monitoring data with graphical presentation for the reporting quarter are shown in Appendix E. A summary on the monitoring results is presented in Table 3.1.
Table 3.1: Summary of Monitoring Data
Parameter |
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|
|
|
|
1 hour TSP
|
AM1 |
19 |
74 |
39 |
AM2 |
25 |
94 |
51 |
|
24 hour TSP
|
AM1 |
7 |
64 |
24 |
AM2 |
8 |
113 |
36 |
|
Construction Noise |
|
|
|
|
Leq(30min) |
NM1A |
67 |
68 |
68 |
Summary of the exceedances in the reporting quarter is tabulated in Table 3.2.
Table 3.2: Summary of Exceedances
Monitoring Station |
Parameter |
No. of Exceedance |
Action Taken |
||
Action Level |
Limit Level |
||||
Air Quality |
|
|
|
|
|
AM1 |
1 hour TSP |
0 |
0 |
N/A |
|
24 hour TSP |
0 |
0 |
N/A |
||
AM2 |
1 hour TSP |
0 |
0 |
N/A |
|
24 hour TSP |
0 |
0 |
N/A |
||
Construction Noise |
|
|
|
|
|
NM1A |
Leq(30min) |
0 |
0 |
N/A |
|
All 1-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance was recorded.
All 24-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance was recorded.
All construction noise monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance was recorded.
All landscape and visual impact inspections were conducted as scheduled in the reporting quarter. No adverse comment on landscape and visual aspects were recorded.
As advised by the Contractor (L2 Contract), 768.14 tonnes, 1233.35 tonnes and 96.63 tonnes of inert C&D material were disposed of as public fill to Tseung Kwan O Area 137, Tuen Mun Area 38, and Chai Wan Public Fill Barging Point respectively in the reporting quarter, while 1565.5 tonnes of general refuse were disposed of at SENT and WENT landfill. 186.6 tonnes of metals, 0.0 tonne of paper/cardboard packaging, 0.0 tonne of plastic and 0.0 tonne of timber were collected by recycling contractors in the reporting quarter. 0.0 tonne of inert C&D materials was reused on site. 0.0 tonne of fill materials was imported for use at site and 0.0 tonne of inert C&D materials was reused in other projects. 549.6 tonnes of inert C&D materials were disposed to sorting facility and 0.0 tonne of chemical waste were collected by licensed contractors in the reporting quarter.
The actual amount of different types of waste generated by the activities of construction works at Lyric Theatre Complex in the reporting quarter are shown in Appendix F.
Six complaints were received in the reporting quarter: 4 complaints in August and 2 complaints in October. No notifications of summons and successful prosecutions were received in the reporting quarter.
On 2 August 2021, WKCDA received a complaint from the office of Mr. Derek Hung (Yau Tsim Mong District Council (YTMDC) member) regarding noise generated from WKCD construction site. The complainant has expressed concern about the construction noise between 19 and 31 July 2021, especially before 9am on 21 and 31 July 2021. The complainant understands that the working hours permitted by the government is 7am-7pm, except public holidays. However, he/she and Derek Hung would like to seek if the noise disturbance could be reduced before 9am. Video shot was also taken by the complainant at 8:50 am on 31 July 2021 to show the evidence of noise generated from WKCD construction site. After the investigation, it was preliminarily believed that the construction noise on 21 July 2021 could be attributable to Lyric Theatre Complex (L2 Contract), which involved breaking works at around 8:45am on 21 July 2021 for residue concrete removal at G/F of LTC area. As the breaker noise was similar to the noise in the video provided by the complainant, it is believed that the breaker was the plausible source of the complaint noise. However, by considering that the permitted working hours for construction works are 7am to 7pm (except for public holidays), the works carried out in Lyric Theatre Complex (L2 Contract) were still within compliance to the local regulations and construction noise permit (CNP) conditions. Nonetheless, the Contractor is recommended to enhance specific noise mitigation measures and avoid noisy works before 9am to minimize disturbance to nearby residents.
On 18 August 2021, the Environmental Protection Department (EPD) has received a complaint regarding dust emission generated from WKCD Zone 2A site and the complaint was referred by EPD on 20 August 2021. The complainant has expressed concern of construction dust generated by rock breaking work at B1/F of Zone 2A site without proper dust mitigation measures. As the complainant specified that the dust impact was from the construction B1/F site of Zone 2A, that is not within the Lyric Theatre Complex site boundary, hence the complaint was not attributable to Lyric Theatre Complex. However, dust control measures will continue to be strictly implemented on site to reduce impacts to nearby residents.
On 19 August 2021, WKCDA has received a complaint from the Office of Mr. Derek Hung (YTMDC member) regarding noise generated from WKCD construction site. The complainant has expressed concern about the construction noise before 9am on 18 and 19 August 2021. The complainant understands that the working hours permitted by the government is 7am-7pm, except public holidays. However, he/she and Mr. Derek Hung would like to seek if the noise disturbance could be reduced before 9am. Video shot was also taken by the complainant at 8:30am on 18 and 19 August 2021 to show the evidence of noise generated from WKCD construction site. After investigation, it was found that no noisy works were undertaken before 9am on 18 and 19 August 2021 for Lyric Theatre Complex (L1 and L2 Contracts). Also, since the major construction works for Lyric Theatre Complex (L1 Contract) were completed by June 2021, no noisy works were undertaken in L1 Contract. In sum, the complaint could not be attributable to Lyric Theatre Complex (L1 and L2 Contract). However, noise mitigation measures will continue to be strictly implemented on site. The contractors are reminded to strengthen the implementation of the recommendations for noise mitigation measures to reduce impacts on nearby residents.
On 27 August 2021, WKCDA received a complaint from the same resident living in The Harbourside through WKCDA Enquiry Hotline and referral by YTMDC Member. The complainant concerned the pile driving carried out in the construction site next to the Lyric Theatre Complex, and claiming that the noise persisted from 8 am to 6 pm. The complainant also enquired about the tentative completion date of the pile driving works. As the complainant specified that the noise was generated from pile driving activities next to the Lyric Theatre Complex, and no pile driving works were involved in Lyric Theatre Complex, hence the complaint was considered to be not attributable to Lyric Theatre Complex. However, noise control measures will continue to be strictly implemented on site to reduce impacts to nearby residents.
On 8 October 2021, EPD received a complaint regarding muddy water discharge near WKCD and referred to WKCDA on 12 October 2021. Two photos were provided by the complainant. As from the photos provided by the complainant, the concerned area was not within Lyric Theatre Complex’s site boundary, hence it could not directly imply the complaint was attributable to Lyric Theatre Complex. However, the contractors are reminded to strictly implement and maintain good site practices to avoid water pollution to the water body of Victoria Harbour.
On 27 October 2021, WKCDA has received a complaint from EPD. The complainant has expressed concern about the construction noise generated from 9am to 9pm even on Sunday. A video and photos were provided by the complainant showing the situation on 25 October 2021. As from the photos and video provided by the complainant, the concerned area was not within Lyric Theatre Complex’s site boundary, hence it could not directly imply the complaint was attributable to Lyric Theatre Complex. However, noise control measures will continue to be strictly implemented on site to reduce impacts to nearby residents.
The cumulative statistics on complaints, notifications of summons and successful prosecutions were provided in Appendix G.
Based on the observations made during site audits, landscape inspections, and construction dust and noise monitoring results, no non-compliances and exceedances of air quality and noise were recorded in the reporting quarter.
Reviewing the implementation of the recommended mitigation measures in the EM&A Manual, it was observed that they were effective and efficient in controlling the potential impacts due to construction of the project during the reporting period. Review of the effectiveness and efficiency of the EM&A programme will continue, and recommendations will be provided to remediate any potential impacts due to the project and to improve the EM&A programme if deficiencies of the existing EM&A programme are identified.
The EM&A programme as recommended in the EM&A Manual has been undertaken. The construction works and EM&A programme for M+ Museum was commenced on 31 October 2015 and completed on 28 February 2021; while the construction works and EM&A programme for Lyric Theatre Complex (L1 and L2 Contracts) was commenced on 1 March 2016, and the EM&A programme for L1 Contract was completed on 30 June 2021.
Monitoring of air quality and noise with respect to the Project is underway. In particular, the 1-hour TSP, 24-hour TSP and noise level (as Leq, 30 minutes) under monitoring have been checked against established Action and Limit levels. There was no breach of Action and Limit levels for Air Quality (1-hour TSP and 24-hour TSP) and Noise in this reporting quarter.
Six complaints were received in the reporting quarter. No notifications of summons and successful prosecutions were received during the reporting quarter.
Weekly construction phase site inspections and bi-weekly landscape and visual impact inspections were conducted during the reporting quarter as required. It was observed that the Contractor had implemented all possible and feasible mitigation measures to mitigate the potential environmental impacts during construction phase works.