Contents
1.3 Construction
Works Status in the Reporting Period
1.4 Summary
of EM&A Requirements and Alternative Monitoring Locations
1.4.2 Alternative
Monitoring Locations
2 Impact
Monitoring Methodology
2.2.1 Monitoring
Parameters, Frequency and Duration
2.3.1 Monitoring
Parameters, Frequency and Duration
3.4 Landscape
and Visual Impact
4 Site
Environmental Management
4.1.1 Zones 2A, 2B
& 2C (Contract No.: CC/2023/2B/095)
4.2 Advice on the Solid and Liquid Waste Management Status
4.2.1 Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095)
4.3 Status
of Environmental Licenses and Permits
4.3.1 Zones
2A, 2B & 2C (Contract No.:
CC/2023/2B/095)
4.4 Recommended
Mitigation Measures
4.4.1 Zones 2A, 2B
& 2C (Contract No.:
CC/2023/2B/095)
Compliance with
Environmental Permit
5 Report
in Non-compliance, Complaints, Notification of Summons and Successful
Prosecutions
5.1 Record
on Non-compliance of Action and Limit Levels
5.2 Record
on Environmental Complaints Received
5.3 Record
on Notifications of Summons and Successful Prosecution
6.1 Construction Works for the Coming
Month(s)
6.2 Key
Issues for the Coming Month
6.2.1 Zones 2A, 2B
& 2C (Contract No.: CC/2023/2B/095)
6.3 Monitoring
Schedule for the Coming Month
7 Conclusions
and Recommendations
Figure 1 Site
Layout Plan and Monitoring Stations
B. Tentative
Construction Programme
C. Action
and Limit Levels for Construction Phase
D. Event
and Action Plan for Air Quality, Noise, Landscape and Visual Impact
G. Graphical
Plots of the Monitoring Results
H. Meteorological
Data Extracted from Hong Kong Observatory
J. Environmental
Mitigation Measures – Implementation Status
K. Cumulative
Statistics on Complaints, Notifications of Summons and Successful Prosecutions
Apex Testing & Certification Limited (Apex) was commissioned to
undertake the Environmental Team (ET) services (including environmental
monitoring and audit (EM&A) for the construction activities in Zone 2A,
consisting of Foundation, Excavation and Lateral Support Works for Integrated
Basement and Underground Road (Contract No.: GW/2020/05/073); Zone 2B
& 2C consisting of Piling Works for Integrated Basement and Underground
Road (Contract No.: CC/2020/2B/088); and Zones 2A, 2B & 2C consisting of
Excavation and Lateral Support Works (Stages 1 & 2) for The Integrated
Basement and Underground Road (Contract No.: CC/2023/2B/095) at WKCD. The
construction works and EM&A programme for Zone 2A (Contract No.:
GW/2020/05/073) was commenced on 03 October 2020 and handed over on 31 March
2023; while the construction works and EM&A programme for Zone 2B & 2C
(Contract No.: CC/2020/2B/088) was commenced on 30 September 2021 and handed
over on 05 July 2024. The construction works and EM&A programme for Zones
2A, 2B & 2C (Contract No.: CC/2023/2B/095) was commenced on 05 July 2024.
The Project Proponent is the West Kowloon Cultural District Authority (WKCDA). The overall works for the WKCD fall under two separate categories of Designated Project (DP) of the Environmental Impact Assessment Ordinance (EIAO), namely an “engineering feasibility study of urban development projects with a study area covering more than 20 ha or involving a total population of more than 100 000” (Item 1 of Schedule 3) and “an underpass more than 100m in length under the built areas” (Item A.9, Part I, Schedule 2). An Environmental Permit No. EP-453/2013/A (EP) was issued with respect to the “Underpass Road and Austin Road Flyover Serving the West Kowloon Cultural District” which specifically includes the abovementioned category of DP under Item A.9, Part I, Schedule 2 of the EIAO.
This Monthly EM&A Report presents the
monitoring works at Zones 2A, 2B & 2C from 01 to 31 July 2025.
Exceedance of Action and Limit Levels
There was no breach of Action or Limit levels for Air Quality (1-hour TSP and 24-hour TSP) and Construction Noise in this reporting month.
Implementation of
Mitigation Measures
Construction phase weekly site inspections were carried out on 04, 09, 17, 24 and 30 July 2025 for Excavation and Lateral Support Works in Zones 2A, 2B & 2C to confirm the implementation measures undertaken by the Contractors in the reporting month. The outcomes are presented in Section 4 and the status of implementation of mitigation measures in the site is shown in Appendix J.
Landscape and visual impact inspections were conducted as part of the above-mentioned weekly site inspections during the reporting month. No adverse comment on landscape and visual aspects was made during these inspections.
Record of Complaints
No environmental complaints were recorded in the reporting month.
Record of Notifications
of Summons and Successful Prosecutions
No notifications of summons and successful prosecutions were recorded in the reporting month.
Future Key Issues
The major site works for Zones 2A, 2B & 2C scheduled to be commissioned in the coming month
include:
· Bored Pile, Pipe Pile and King Post Works
· Jet Grouting Works
Potential environmental impacts due to the construction activities, including air, noise, water quality, waste, landscape and visual, will be monitored or reviewed. The recommended environmental mitigation measures shall be implemented on site and regular inspections as required will be carried out to ensure that the environmental conditions are acceptable.
Apex Testing & Certification Limited (Apex) was commissioned to
undertake the Environmental Team (ET) services (including environmental
monitoring and audit (EM&A)) for the construction activities in Zone 2A,
consisting of Foundation, Excavation and Lateral Support Works for Integrated
Basement and Underground Road (Contract No.: GW/2020/05/073); Zone 2B
& 2C consisting of Piling Works for Integrated Basement and Underground
Road (Contract No.: CC/2020/2B/088); and Zones 2A, 2B & 2C consisting of
Excavation and Lateral Support Works (Stages 1 & 2) for The Integrated
Basement and Underground Road (Contract No.: CC/2023/2B/095) at WKCD. The
purpose of the development in Zone 2A and Zone 2B & 2C is to reserve for
Integrated Basement (IB) and Underground Road (UR). The Zone 2A construction
activities involve the foundation, excavation and lateral support (ELS) works,
road works, drainage diversion works, and temporary car parking. The Zone 2B
& 2C construction activities involve the piling works. The construction
works and EM&A programme for Zone 2A (Contract No.: GW/2020/05/073) was
commenced on 03 October 2020 and handed over on 31 March 2023; while the
construction works and EM&A programme for Zone 2B & 2C (Contract No.:
CC/2020/2B/088) was commenced on 30 September 2021 and handed over on 05 July
2024. The construction works and EM&A programme for Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095)
was commenced on 05 July 2024.
The overall works for the WKCD fall under two separate categories of
Designated Project (DP) of the Environmental Impact Assessment Ordinance
(EIAO), namely an “engineering feasibility study of urban development projects
with a study area covering more than 20 ha or involving a total population of
more than 100 000” (Item 1 of Schedule 3) and “an underpass more than 100m in
length under the built areas” (Item A.9, Part I, Schedule 2). An Environmental
Permit No. EP-453/2013/A (EP) was issued with
respect to the “Underpass Road and Austin Road Flyover Serving the West Kowloon
Cultural District” which specifically includes the abovementioned category of
DP under Item A.9, Part I, Schedule 2 of the EIAO. The captioned projects
include part of the abovementioned underpass road located within the site
boundary falls under this same category.
The Monthly EM&A Report is prepared in accordance with the Condition 3.4 of the Environmental Permit No. EP-453/2013/A. This Monthly EM&A Report presents the monitoring works at 2A, 2B & 2C from 01 to 31 July 2025. The purpose of this report is to summarise the findings in the EM&A of the project over the reporting period.
The
organisation chart and lines of communication with respect to the on-site
environmental management structure together with the contact information of the
key personnel are shown in Appendix A.
During the reporting period, construction works at Zones 2A, 2B & 2C undertaken include:
· Bored Pile, Pipe Pile and King Post Works
· Jet Grouting Works
The Construction Works Programme of Zones 2A, 2B & 2C is provided in Appendix
B. A layout plan of the Project is provided in Figure 1. Please refer to Table 4.3 on
the status of the environmental licenses.
The EM&A programme requires environmental monitoring of air quality, noise, landscape and visual as specified in the approved EM&A Manual.
A summary of impact EM&A requirements is presented in Table 1.1.
Table 1.1: Summary of Impact EM&A Requirements
Parameters |
Descriptions |
Locations |
Frequencies |
Air Quality |
24-Hours TSP |
AM3-The Victoria Towers Tower 1 |
At least once every 6 days |
1-Hour TSP |
AM3-The Victoria Towers Tower 1 |
At least 3 times every 6 days |
|
24-Hours TSP |
AM4-Canton Road Government Primary School |
At least once every 6 days |
|
1-Hour TSP |
AM4-Canton Road Government Primary School |
At least 3 times every 6 days |
|
24-Hours TSP |
AM5-Topside Developments at West Kowloon Terminus Site |
At least once every 6 days |
|
1-Hour TSP |
AM5-Topside Developments at West Kowloon Terminus Site |
At least 3 times every 6 days |
|
Noise |
Leq, 30 minutes |
NM2-The Arch, Sun Tower |
Weekly |
Leq, 30 minutes |
NM3-The Victoria Towers Tower 1 |
Weekly |
|
Leq, 30 minutes |
NM4-Canton Road Government Primary School |
Weekly |
|
Leq, 30 minutes |
NM5-Development next to Austin Station |
Weekly |
|
Landscape & Visual |
Monitor implementation of proposed mitigation measures during the
construction stage |
As described in Table 9.1 and 9.2 of the EM&A Manual |
Bi-Weekly |
The EM&A
programme for the Project should require 5 noise monitoring station and 5 air
quality monitoring stations located closest to the Project area. With regard to the monitoring activities
at M+ Museum and the Lyric Complex, three monitoring stations had been
considered, including AM1 (International Commerce Centre), AM2 (The Harbourside
Tower 1) for air monitoring, and NM1 (The Harbourside Tower 1) for noise
monitoring.
In the context of the construction
activities in Zone 2A and Zone 2B & 2C, all other monitoring locations
including AM3 (The Victoria Towers
Tower 1), AM4 (Canton Road Government Primary School), and AM5 (Topside
Developments at West Kowloon Terminus Site) for air monitoring; and NM2 (The Arch, Sun Tower), NM3 (The Victoria Towers Tower 1), NM4 (Canton
Road Government Primary School) and NM5 (Development next to Austin Station) for noise
monitoring, have
been taken into account. However, access to all these originally designated
monitoring stations was declined as described below point-by-point.
The Arch management office and owners’
committee have formally declined the proposal of setting up noise monitoring
instrument on its premises at the podium level of Sun Tower (NM2) on 24 July
2014. Thus, alternative
noise monitoring location was identified at the ground floor in front of The Arch – Sun Tower (NM2A),
which is at the same location as stated in the EM&A Manual for consistency. No management
approval is required at the ground floor for conducting the noise monitoring. This alternative air monitoring location was approved by EPD on 29
September 2020.
The Victoria Towers management
office formally declined the proposal of setting up air
quality and noise monitoring instruments on its premises at the podium area
of Tower 1 (AM3/NM3) on 16 June 2020. Alternative air monitoring location was
identified at ground floor at the Northeast corner of West Kowloon Station’s
station box (AM3A), in the same direction to the area of major construction
site activities in Zone 2A. This alternative air monitoring location was
approved by EPD on 29 September 2020. An alternative noise monitoring location
was identified at the ground floor in front of the Xiqu Centre (NM3A), which is
set closer to the construction site boundary with more direct line sight to the
major site activities and higher exposure to the construction noise with no
disturbance to the premises’ occupants during noise monitoring activities. No
management approval is required at the ground floor for conducting the noise
monitoring. This alternative air monitoring location was approved by EPD on 29
September 2020.
Canton Road Government Primary
School formally declined the proposal of setting up air
quality and noise monitoring instruments on its premise at the podium level (AM4/NM4) on 16 June 2020. Alternative air monitoring
location was identified at ground floor at the Southeast corner of West Kowloon Station’s station box
(AM4A), in same direction to the area of major construction site activities in
Zone 2A. This alternative air monitoring location was approved by EPD on 29
September 2020. An alternative noise monitoring
location was identified at the ground floor next to Tsim
Sha Tsui Fire Station (NM4A), which is set closer to the construction site
boundary with more direct line sight to the major site activities and higher
exposure to the construction noise with no disturbance to the premises’ occupants during noise monitoring
activities. No management approval is required at the ground floor for
conducting the noise monitoring. This alternative air monitoring location was
approved by EPD on 29 September 2020.
MTR also formally declined the
access to the designated AM5 location (topside developments at West Kowloon
Terminus Site) on 15 July 2020. Alternative air monitoring location was
identified at ground floor at the North
of West Kowloon Station’s station box (AM5A), in same direction
to the area of major construction site activities in Zone 2A. This alternative
air monitoring location was approved by EPD on 29 September 2020.
Grand Austin property management
office formally declined our proposal of setting up noise monitoring instrument on its premises at the podium
level (NM5) on 10 July 2020. Alternative noise monitoring location was
identified at the Pedestrian road (ground floor) outside West Kowloon Station
(NM5A), which is set closer to the
construction site boundary with more direct line sight to the major site
activities and higher exposure to the construction noise with no disturbance to
the premises’ occupants during noise monitoring activities. No management
approval is required at the ground floor for conducting the noise monitoring.
This alternative air monitoring location was approved by EPD on 29 September
2020.
The Environmental Quality Performance Limits for air quality and noise are shown in Appendix C.
The Event and Action Plan for air quality, construction noise, and landscape and visual are shown in Appendix D.
The EM&A programme followed
the recommended mitigation measures in the EM&A Manual. The EM&A
requirements as well as the summary of implementation status of the
environmental mitigation measures are provided in Appendix J.
Air quality and noise monitoring
methodology, including the monitoring locations, equipment used, parameters, frequency
and duration etc., are described in this Section. The environmental monitoring
schedules for the reporting period and the tentative monitoring Schedule for
the coming month are provided in Appendix
E.
The relevant EM&A monitoring
requirements and details for landscape and audit impact, are also presented in
this Section.
Table 2.1 summarizes the monitoring
parameters, frequency and duration of the TSP monitoring.
Table
2.1: Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency |
Duration |
24-hour TSP |
At least once in every six-days |
24 hours |
1-hour TSP |
At least 3 times every six-days |
60 minutes |
Monitoring
stations and locations are given in Table
2.2 and shown in Figure
1.
Table 2.2: Air Quality Monitoring Station
Monitoring Station |
Location Description |
AM3A |
Northeast corner of West Kowloon Station’s station box
(G/F) |
AM4A |
Southeast corner of West Kowloon Station’s station box
(G/F) |
AM5A |
North of West Kowloon Station’s station box (G/F) |
Continuous 24-hour TSP air quality monitoring was conducted using High Volume Sampler (HVS) (Model: TE-5170) located at the designated monitoring station. The HVS meets all the requirements stated in of the EM&A Manual. Portable direct reading dust meter was used to carry out the 1-hour TSP monitoring. Table 2.3 summarizes the equipment used in the impact air quality monitoring. Copies of the calibration certificates for the HVS, calibration kit and portable dust meters are attached in Appendix F.
Table 2.3: TSP
Monitoring Equipment
Equipment |
Model |
24-hour TSP monitoring |
|
High Volume Sampler |
TE-5170 (Serial No.: 4340; 3998; 4344) |
Calibrator |
TE-5025A (Orifice I.D.: 4088) |
1-hour TSP monitoring |
|
Portable direct reading dust meter |
Sibata-LD-3B (Serial No.: 276004,
336338, 476672) |
The 1-hour TSP monitoring should be determined periodically (e.g. annually) by the HVS to check the validity and accuracy of the results measured by direct reading method.
24-hour TSP Monitoring
Installation
The HVS was installed at the site boundary. The following criteria were considered in the installation of the HVS.
– A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
– The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
– A minimum of 2 metres separation from walls, parapets and penthouse was required for rooftop sampler.
– A minimum of 2 metres separation from any supporting structure, measured horizontally was required.
– No furnace or incinerator flues or building vent were nearby.
– Airflow around the sampler was unrestricted.
– The sampler has been more than 20 metres from any drip line.
– Permission was obtained to set up the sampler and to obtain access to the monitoring station.
– A secured supply of electricity is needed to operate the sampler.
Preparation of Filter
Papers
– Glass fibre filters were labelled and sufficient filters that were clean and without pinholes were selected.
– The filters used are specified to have a minimum collection efficiency of 99 percent for 0.3 µm (DOP) particles.
– All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C with relative humidity (RH) < 50% and was not variable by more than ±5 %. A convenient working RH was 40%. All preparation of filters was done by Hong Kong Laboratory Accreditation Scheme (HOKLAS) accredited laboratory.
Field Monitoring
Procedures
– The power supply was checked to ensure the HVS works properly.
– The filter holder and the area surrounding the filter were cleaned.
– The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
– The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
– The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to avoid air leakage at the edges.
– The shelter lid was closed and was secured with the aluminium strip.
– The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
– A new flow rate record sheet was set into the flow recorder.
– The flow rate of the HVS was checked and adjusted at around 1.3 m3/min. The range specified in the EM&A Manual was between 0.6-1.7 m3/min.
– The programmable timer was set for a sampling period of 24 hours, and the starting time, weather condition and the filter number were recorded.
– The initial elapsed time was recorded.
– At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
– It was then placed in a clean plastic envelope and sealed.
– All monitoring information was recorded on a standard data sheet.
– Filters were sent to a Hong Kong Laboratory Accreditation Scheme (HOKLAS) accredited laboratory for analysis.
Maintenance and
Calibration
– The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
– HVSs were calibrated upon installation and thereafter at bi-monthly intervals. The calibration kits were calibrated annually.
– Calibration records for HVS and calibration kit are shown in Appendix F.
1-hour TSP Monitoring
Field Monitoring
The measuring procedures of the 1-hour dust meter are in accordance with
the Manufacturer’s Instruction Manual as follows:
– Turn the power on.
– Close the air collecting opening cover.
– Push the “TIME SETTING” switch to [BG].
– Push “START/STOP” switch to perform background measurement for 6 seconds.
– Turn the knob at SENSI ADJ position to insert the light scattering plate.
– Leave the equipment for 1 minute upon “SPAN CHECK” is indicated in the display.
– Push “START/STOP” switch to perform automatic sensitivity adjustment. This measurement takes 1 minute.
– Pull out the knob and return it to MEASURE position.
– Setting time period of 1 hour for the 1-hour TSP measurement.
– Push “START/STOP” to start the 1-hour TSP measurement.
– Regular checking of the time period setting to ensure monitoring time of 1 hour.
Maintenance and Calibration
– The 1-hour dust meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality monitoring.
– Calibration records for direct dust meters are shown in Appendix F.
Weather Condition
– Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix H.
Table 2.4 summarizes the monitoring parameters,
frequency and duration of noise monitoring. The noise in A-weighted levels Leq,
L10 and L90 are recorded in a 30-minute interval between
0700 and 1900 hours.
Table 2.4: Noise Monitoring Parameters, Period and Frequency
Time Period |
Parameters |
Frequency |
Daytime
on normal weekdays (0700-1900
hours) |
Leq(30
min), L90(30 min) & L10(30 min) |
Once
every week |
Note: *70 dB(A) for schools and 65 dB(A) during school examination
periods.
If works are to be carried out during restricted hours, the conditions
stipulated in the Construction Noise Permit (CNP) issued by the Noise Control
Authority have to be followed.
Noise monitoring stations and locations are given in Table
2.5 and shown in Figure
1.
Table 2.5: Noise Monitoring Station
Monitoring Station |
Location |
NM2A |
|
NM3A |
|
NM4A |
Next to Tsim Sha Tsui Fire Station (G/F) |
NM5A |
Pedestrian road (G/F) outside West Kowloon
Station |
Integrating Sound Level Meter was used for noise monitoring. It was a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (LAeq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 2.6 summarizes the noise monitoring equipment model being used.
Table 2.6: Noise Monitoring Equipment
Equipment Model |
|
Integrating Sound Level Meter |
Calibrator |
AWA5661 (Serial No.: 341483) |
Quest
QC-10 (Serial No.: Q19010183) |
Field Monitoring
– The microphone of the Sound Level Meter was set at least 1.2 m above the ground.
– Free Field measurement was made at NM5A monitoring location.
– The battery condition was checked to ensure the correct functioning of the meter.
– Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 30 minutes intervals (between 0700-1900 on normal weekdays)
– Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1 kHz. If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid and has to be repeated after re-calibration or repair of the equipment.
– During the monitoring period, the Leq, L10 and L90 were recorded. In addition, any site observations and noise sources were recorded on a standard record sheet.
– A correction of +3dB(A) was made to the free field measurements.
Maintenance and Calibration
– The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.
– The sound level meter and calibrator are sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
– Calibration records are shown in Appendix F.
Weather Condition
– Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix H.
Table 2.7 details the monitoring program (as proposed in the WKCD EIA report) for landscape and visual impact during the construction phase.
Table 2.7: Monitoring Program for Landscape and Visual Impact during Construction Phase
Stage |
Monitoring
Task |
Frequency |
Report |
Approval |
Construction |
Monitor implementation of proposed mitigation
measures during the construction stage. |
Bi-weekly |
ET to report on Contractor’s compliance |
Counter-signed by IEC |
During the landscape and visual impact monitoring, any changes in relation to the landscape and visual amenity should be monitored with reference to the baseline conditions of the site. In addition, mitigation measures were proposed in the WKCD EIA report to minimise the landscape and visual impacts during the construction phase. The proposed mitigation measures as shown in Table 9.1 and Table 9.2 of the EM&A Manual should be checked for proper implementation.
Air quality, noise
and landscape and visual impact
monitoring was undertaken in compliance
with the EM&A Manual during the reporting
month.
Results of 1-hour TSP are summarised in Table 3.1. Graphical plots of the monitoring results are shown in Appendix G.
Table 3.1: Summary
of 1-hour TSP monitoring results
Monitoring Station |
Monitoring Date |
Start Time |
1-hour TSP (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
||
1st Result |
2nd Result |
3rd Result |
||||||
AM3A |
05-Jul-25 |
7:05 |
39 |
34 |
36 |
34-47 |
280.4 |
500 |
11-Jul-25 |
13:00 |
40 |
45 |
47 |
||||
17-Jul-25 |
7:03 |
38 |
43 |
38 |
||||
23-Jul-25 |
13:04 |
45 |
47 |
44 |
||||
29-Jul-25 |
7:00 |
36 |
36 |
37 |
||||
AM4A |
05-Jul-25 |
7:13 |
32 |
38 |
40 |
32-49 |
278.5 |
500 |
11-Jul-25 |
13:08 |
46 |
42 |
42 |
||||
17-Jul-25 |
7:11 |
43 |
41 |
42 |
||||
23-Jul-25 |
13:12 |
49 |
43 |
44 |
||||
29-Jul-25 |
7:08 |
41 |
38 |
37 |
||||
AM5A |
05-Jul-25 |
7:28 |
37 |
31 |
32 |
31-46 |
275.4 |
500 |
11-Jul-25 |
13:25 |
46 |
42 |
41 |
||||
17-Jul-25 |
7:26 |
36 |
36 |
42 |
||||
23-Jul-25 |
13:29 |
45 |
41 |
43 |
||||
29-Jul-25 |
7:23 |
38 |
34 |
39 |
Results of 24-hour TSP are summarised in Table 3.2.
Graphical plots of the monitoring results are shown in Appendix G.
Table 3.2: Summary
of 24-hour TSP monitoring results
Monitoring Station |
Monitoring Date |
Start Time |
Monitoring Results (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
AM3A |
05-Jul-25 |
10:00 |
33.3 |
31.5-42.9 |
152.4 |
260 |
11-Jul-25 |
10:00 |
37.8 |
||||
17-Jul-25 |
10:00 |
35.0 |
||||
23-Jul-25 |
10:00 |
42.9 |
||||
29-Jul-25 |
10:00 |
31.5 |
||||
AM4A |
05-Jul-25 |
10:00 |
33.5 |
33.5-42.2 |
152.6 |
260 |
11-Jul-25 |
10:00 |
42.2 |
||||
17-Jul-25 |
10:00 |
40.3 |
||||
23-Jul-25 |
10:00 |
41.9 |
||||
29-Jul-25 |
10:00 |
34.3 |
||||
AM5A |
05-Jul-25 |
10:00 |
30.7 |
30.7-40.9 |
141.1 |
260 |
11-Jul-25 |
10:00 |
40.9 |
||||
17-Jul-25 |
10:00 |
35.4 |
||||
23-Jul-25 |
10:00 |
37.5 |
||||
29-Jul-25 |
10:00 |
32.8 |
No exceedance of 1-hour and 24-hour TSP (Action or Limit Level) was recorded in the reporting period.
The construction noise monitoring results are summarized in Table 3.3. Graphical plots of the monitoring data and the station set-up as façade and free-field measurements are shown in Appendix G.
Table 3.3: Summary
of noise monitoring results during normal weekdays
Monitoring Stations |
Monitoring
Date |
Start Time |
End Time |
Leq
(30 mins) dB(A) |
Limit Level
for Leq (dB(A)) |
NM2A |
05-Jul-25 |
07:05 |
07:30 |
62.9 |
75 |
11-Jul-25 |
14:00 |
14:25 |
62.5 |
||
17-Jul-25 |
07:03 |
07:28 |
62.7 |
||
23-Jul-25 |
14:02 |
14:27 |
62.6 |
||
29-Jul-25 |
07:00 |
07:25 |
62.9 |
||
NM3A |
05-Jul-25 |
08:35 |
09:00 |
60.8 |
75 |
11-Jul-25 |
15:21 |
15:46 |
61.1 |
||
17-Jul-25 |
08:33 |
09:58 |
60.9 |
||
23-Jul-25 |
15:27 |
15:52 |
60.5 |
||
29-Jul-25 |
08:39 |
09:04 |
60.7 |
||
05-Jul-25 |
10:40 |
11:05 |
58.2 |
70/65^# |
|
11-Jul-25 |
15:56 |
16:21 |
58.2 |
||
17-Jul-25 |
10:38 |
11:03 |
58.3 |
||
23-Jul-25 |
16:02 |
16:27 |
58.5 |
||
29-Jul-25 |
10:44 |
11:09 |
58.4 |
||
NM5A* |
05-Jul-25 |
07:55 |
08:20 |
63.5 |
75 |
11-Jul-25 |
14:40 |
15:05 |
63.7 |
||
17-Jul-25 |
07:53 |
08:18 |
63.6 |
||
23-Jul-25 |
14:40 |
15:14 |
63.6 |
||
29-Jul-25 |
07:50 |
08:24 |
63.9 |
Remarks: * +3dB (A) correction was applied to free-field measurement. ^
70 dB(A) for schools and 65 dB(A) during school examination
periods. # No school examination was
conducted during reporting period. |
No exceedance of Construction
Noise (Action or Limit Level) was recorded in the reporting month
Construction Noise
Permits for the works carried out during restricted hours were obtained and
listed in Table 4.3.
Landscape and visual impact inspections were conducted as part of the weekly site inspections on 04, 17 and 30 July 2025 for Zones 2A, 2B & 2C during the reporting month. As reviewed by the registered Landscape Architect, no adverse comment on landscape and visual aspects was made during these inspections.
The landscape and visual mitigation measures were implemented during the reporting period. The summary of implementation status of the environmental mitigation measures is provided in Appendix J.
Construction phase weekly site
inspections were carried out on 04, 09, 17, 24 and 30 July 2025 at Zones
2A, 2B & 2C. The joint site inspection with IEC, ET, ER and Contractor for
Zones 2A, 2B & 2C was held on 09 July 2025. All observations have been recorded in the site inspection
checklist and passed to the Contractor together with the appropriate
recommended mitigation measures where necessary.
The key
observations from the site inspections and associated recommendations are
summarized in Table 4..
Table 4.1: Summary
of Site Inspections and Recommendations for Zones 2A, 2B & 2C
Inspection Date |
Parameter |
Observation / Recommendation |
Contactor’s Responses / Action(s) Undertaken |
Close-out (Date) |
04-Jul-25 |
Air Quality & Water
Quality |
The contractor was reminded that dust suppression
measures shall be strengthened at the access road
to minimize dust impact. The contractor was reminded that the concrete
bound barriers shall be maintained properly at the seafront to prevent
wastewater flow into the nearby sea. The
contractor was reminded to maintain proper gradient on road and avoid local
pit to facilitate the runoff collection of the sump pit and avoid stagnant
water. |
Water hose was ready on site. Dust suppression
using water spraying was conducted. Damaged runoff barrier was reinstated. Local pit
was filled and the road gradient was adjusted to ensure proper water
collection ability of the sump pit. |
07-Jul-25 |
09-Jul-25 |
Waste Management & Water
Quality & Other |
The contractor was reminded to have better
housekeeping and dispose of general refuse frequently at designated areas and
to avoid accumulation on site which may lead to hygiene problems. The contractor was reminded that fuel drum shall
not be stored in designated areas which have pollution prevention facilities
or drip trays with adequate capacity. The contractor was reminded to ensure proper
management of plants on site so as to avoid potential insect and mosquito
activity in the area. |
General refuse was disposed. Fuel drum was removed. Unnecessary plant was removed. |
11-Jul-25 |
17-Jul-25 |
Water
Quality & Waste Management |
The contractor was reminded to clean up the
deposited silt and water to avoid any potential leakage overflow. The contractor was reminded to have better
housekeeping and dispose of general refuse frequently at designated areas and
to avoid accumulation on site which may lead to hygiene problems. |
Stagnant water on the haul road was removed. General refuse was removed. |
23-Jul-25 |
24-Jul-25 |
Water
Quality & Waste Management |
The contractor was reminded that fuel drum shall
not be stored in designated areas which have pollution prevention facilities
or drip trays with adequate capacity. The contractor was reminded to have better
housekeeping and dispose of general refuse frequently at designated areas and
to avoid accumulation on site which may lead to hygiene problems. The
contractor was reminded to clean up the deposited silt and water to avoid any
potential leakage overflow. The water pump should be provided. The
contractor was reminded to provide the proper management of the drainage
system. |
Fuel drums were removed. General
refuse was collected and the site was tidied. Water
pump was deployed to eliminate the stagnant water. The
leakage was sealed. |
25-Jul-25 |
30-Jul-25 |
Water Quality |
The contractor was reminded to clean up the
deposited silt and water to avoid any potential leakage overflow. The contractor was reminded to clean the water
tank. The
contractor was reminded that the concrete bound barriers shall be maintained
properly at the seafront to prevent wastewater flow into the nearby sea. The contractor was reminded that the construction
water barrier should be reinforced. |
Stagnant water was removed. Treatment
plant was cleaned. Runoff
barrier was reinstated. Construction
water barrier was strengthened. |
04-Aug-25 |
The Contractors have been
registered as a chemical waste producer for the Project. Construction and
demolition (C&D) material sorting will be carried out on site. A sufficient
number of receptacles were available for general refuse collection.
As
advised by the Zones 2A, 2B & 2C Contractor, 8018.38 tonne and 89.22 tonne of inert C&D material
were disposed of as public fill to Tseung Kwan O Area 137 Public Fill and Tuen
Mun Area 38 Public Fill respectively, while 76.61 tonne of general refuse were disposed
of at SENT landfill. 4.19 tonne of metals, 0.0 tonne of
paper/cardboard packaging, 0.0 tonne of plastics and 0.0 tonne of timber was
collected by recycling contractors in the reporting month. 0.00 tonne of inert
C&D material were reused on site. 3799.18 tonne of inert C&D material
were reused in other projects and 0.0 tonne of inert C&D material was
imported for reuse at site in the reporting month. 0.0 tonne of inert C&D material
was disposed to sorting facility and 0.0 tonne of chemical waste was collected by licensed contractors in the
reporting period.
The cumulative waste generation
records for Zones 2A, 2B & 2C are shown in Appendix I.
The environmental permits,
licenses, and/or notifications on environmental protection for this Project
which were valid during the period are summarised in Table 4.3.
The environmental permits,
licenses, and/or notifications on environmental protection for this Project
which were valid during the period are summarised in Table 4..
Table 4.3: Status
of Environmental Submissions, Licenses and Permits for Zones 2A, 2B & 2C
Permit /
License No. /
Notification / Reference
No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Chemical
Waste Producer Registration |
||||
WPN5117-256-V1011-40 |
11-Jul-24 |
-- |
Valid |
-- |
Billing
Account Construction Waste Disposal |
||||
7051739 |
01-Aug-24 |
-- |
Account Active |
-- |
Construction
Noise Permit |
||||
GW-RE0383-25 |
08-Apr-25 |
30-Sep-25 |
Valid |
- |
PP-RE0010-25 |
07-Apr-25 |
30-Sep-25 |
Valid |
|
Wastewater Discharge License |
||||
WT00045374-2024 |
24-Oct-24 |
31-Oct-2029 |
Valid |
-- |
Notification under Air Pollution Control
(Construction Dust) Regulation |
||||
10006790 |
11-Jul-24 |
-- |
Notified |
-- |
The EM&A programme followed
the recommended mitigation measures in the EM&A Manual. The EM&A
requirements as well as the summary of implementation status of the
environmental mitigation measures are provided in Appendix J. In particular, the following mitigation measures were
brought to attention during the site inspections:
– Dust
suppression measures shall be strengthened at the access road to minimize dust
impact.
Waste Management
– Better
housekeeping shall be strengthened to avoid accumulation on site which may lead
to hygiene problem.
Water Quality
– The concrete
bound barriers shall be maintained properly at the seafront to prevent
wastewater flow into the nearby sea.
– Local
pit shall be
filled and the road gradient shall be adjusted to ensure proper water collection ability
of the sump pit.
– Fuel
drum shall not be stored in designated areas which have pollution prevention
facilities or drip trays with adequate capacity.
– The deposited
silt and water shall
be cleaned up
to avoid any potential leakage overflow. The water pump should be provided.
– The water tank shall be cleaned.
– Construction
water barrier shall
be strengthened.
Other
– Proper
management of plants on site shall be ensured to avoid potential insect and mosquito
activity in the area.
The status
of the required submission under the EP during the reporting period is
summarized in Table 0.1.
Table 0.1: Status of Submissions under the Environmental Permit
EP Condition |
Submission |
Submission
Date |
Condition 3.4 |
Monthly EM&A
Report for June 2025 |
15 July 2025 |
There was no breach of Action or Limit levels for Air Quality (1-hour TSP and 24-hour TSP) and Construction Noise in this reporting month.
No environmental complaint was received in the
reporting month.
The cumulative statistics on complaints were
provided in Appendix K.
No notifications of summons or successful prosecutions were received this month. The cumulative statistics on notifications of summons and successful prosecutions were provided in Appendix K.
The major
site works for Zones 2A, 2B & 2C scheduled to be commissioned in the coming
month include:
· Bored Pile, Pipe Pile and King Post Works
· Jet Grouting Works
Key issues to be considered in
the coming month include:
● Generation of dust from
construction works;
● Noise impact from piling works;
● Generation of site surface
runoffs and wastewater from activities on-site;
● Management of stockpiles and
slopes, particularly on rainy days;
● Sorting, recycling, storage and
disposal of general refuse and construction waste; and
● Management of chemicals and
avoidance of oil spillage on-site.
The environmental site inspection and environmental monitoring will be continued in the coming month. The tentative monitoring schedule for the coming month is shown in the Appendix E.
The EM&A programme as recommended in the EM&A Manual has been undertaken. The construction works and EM&A programme for Zone 2A (Contract No.: GW/2020/05/073) was commenced on 03 October 2020 and handed over on 31 March 2023; while the construction works and EM&A programme for Zone 2B & 2C (Contract No.: CC/2020/2B/088) was commenced on 30 September 2021 and handed over on 05 July 2024. The construction works and EM&A programme for Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) was commenced on 05 July 2024.
Monitoring of air quality and noise with respect to the Projects is
underway. In particular, the 1-hour TSP, 24-hour TSP, Noise
Level (as Leq, 30 minutes) under monitoring have been checked
against established Action and Limit levels. There was no breach of Action
or Limit levels for Air Quality (1-hour TSP and 24-hour TSP) and Construction
Noise in this reporting month.
No environmental complaints were recorded in the
reporting month. No notifications of summons or successful prosecutions were
received during the reporting month.
Weekly
construction phase site inspections and bi-weekly landscape and visual impact
inspections were conducted during the reporting month as required. It was
observed that the Contractors had implemented all possible and feasible
mitigation measures to mitigate the potential environmental impacts during
construction phase works.
Potential environmental impacts
due to the construction activities, including air quality, noise, water quality, waste, landscape and visual, will
be monitored or reviewed. The recommended environmental mitigation measures
shall be implemented on site and regular inspections as required will be
carried out to ensure that the environmental conditions are acceptable.