Contents
1.3 Construction Works Status in
the Reporting Period
1.4 Summary of EM&A
Requirements and Alternative Monitoring Locations
1.4.2 Alternative
Monitoring Locations
2 Impact Monitoring
Methodology
2.2.1 Monitoring
Parameters, Frequency and Duration
2.3.1 Monitoring
Parameters, Frequency and Duration
3.4 Landscape and Visual Impact
4 Site Environmental
Management
4.2 Advice on the Solid and Liquid Waste
Management Status
4.3 Status of Environmental
Licenses and Permits
4.4 Recommended Mitigation
Measures
5 Compliance with
Environmental Permit
6 Report in
Non-compliance, Complaints, Notification of Summons and Successful
Prosecutions
6.1 Record on Non-compliance of
Action and Limit Levels
6.2 Record on Environmental
Complaints Received
6.3 Record on Notifications of
Summons and Successful Prosecution
7.1 Construction Works for the Coming
Month(s)
7.2 Key Issues for the Coming
Month
7.3 Monitoring
Schedule for the Coming Month
8 Conclusions and
Recommendations
Figure 1 Site
Layout Plan and Monitoring Stations
B. Tentative
Construction Programme
C. Action
and Limit Levels for Construction Phase
D. Event
and Action Plan for Air Quality, Noise, Landscape and Visual Impact
G. Graphical
Plots of the Monitoring Results
H. Meteorological
Data Extracted from Hong Kong Observatory
J. Environmental
Mitigation Measures – Implementation Status
K. Cumulative
Statistics on Complaints, Notifications of Summons and Successful Prosecutions
Apex
Testing & Certification Limited (Apex) was commissioned to undertake the
Environmental Team (ET) services (including environmental monitoring and audit (EM&A))
for the construction activities in Zone 2A, consisting of Foundation,
Excavation and Lateral Support Works for Integrated Basement and Underground
Road (Contract No.: GW/2020/05/073); and Zone 2B & 2C consisting of Piling
Works for Integrated Basement and Underground Road (Contract No.: CC/2020/2B/088)
at WKCD. The major construction works and EM&A programme for Zone 2A and
Zone 2B & 2C commenced on 03 October 2020 and 30 September 2021
respectively.
The Project Proponent is the West Kowloon Cultural District Authority (WKCDA). The overall works for the WKCD fall under two separate categories of Designated Project (DP) of the Environmental Impact Assessment Ordinance (EIAO), namely an “engineering feasibility study of urban development projects with a study area covering more than 20 ha or involving a total population of more than 100 000” (Item 1 of Schedule 3) and “an underpass more than 100m in length under the built areas” (Item A.9, Part I, Schedule 2). An Environmental Permit No. EP-453/2013/B (EP) was issued with respect to the “Underpass Road and Austin Road Flyover Serving the West Kowloon Cultural District” which specifically includes the abovementioned category of DP under Item A.9, Part I, Schedule 2 of the EIAO.
This Monthly EM&A Report presents the monitoring works at Zone 2A and Zone 2B & 2C from 01 to 31 March 2022.
Exceedance
of Action and Limit Levels
There was no breach of Action or Limit levels for Air Quality (1-hour TSP and 24-hour TSP) in this reporting month.
Two Action Level exceedances due to two complaints with no Limit Level exceedance of construction noise was recorded in the reporting month.
Implementation of Mitigation Measures
Construction phase weekly site inspections were carried out on 03, 10, 17, 24 and 31 March 2022 for Foundation, Excavation and Lateral Support Works in Zone 2A and on 01, 08, 15, 22 and 29 March 2022 for Piling Works in Zone 2B & 2C to confirm the implementation measures undertaken by the Contractors in the reporting month. The outcomes are presented in Section 4 and the status of implementation of mitigation measures in the site is shown in Appendix J.
Landscape and visual impact inspections were conducted as part of the abovementioned weekly site inspections during the reporting month. No adverse comment on landscape and visual aspects was made during these inspections.
EPD inspection
was conducted at Zone 2B & 2C on 29 March 2022.
Record of Complaints
Five environmental complaints were recorded in the reporting month.
Record of Notifications of Summons and
Successful Prosecutions
No notifications of summons and successful prosecutions were recorded in the reporting month.
Future Key Issues
The major site works for Zone 2A scheduled to be commissioned in the
coming month include:
Zone 2A-1
● ELS (Stage 1) – Grouting / Pipe Pile Works
– King Post & Erection of Steel Column for Working Platform
– Stage 2 Grouting
– Pumping Test
Zone 2A-2
● ELS (Stage 1) – Grouting / Pipe Pile Works
– King Post & Erection of Steel Column for Working Platform
– Pipe Pile Construction
– Stage 2 Grouting
The major site works for Zone 2B & 2C scheduled to be commissioned
in the coming month include:
KD01 (Stage 1-1), KD05 (Section 1), KD06 (Section
2)
● Bored Pile Works
– Predrilling, RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation
KD02 (Stage 5-1)
● Bored Pile Works
– Airlifting, Cage Installation & Concreting and Excavation
KD03 (Stage 3-1)
– Predrilling
KD07 (Section 3), KD08 (Section 4), KD09 (Section 5)
● Trial Pile Works
– RCD
Drilling, Airlifting, Cage Installation &
Concreting and Excavation
● Bored Pile Works
– Predrilling,
RCD Drilling, Airlifting,
Cage Installation & Concreting and Excavation
Potential environmental impacts due to the construction activities, including air, noise, water quality, waste, landscape and visual, will be monitored or reviewed. The recommended environmental mitigation measures shall be implemented on site and regular inspections as required will be carried out to ensure that the environmental conditions are acceptable.
Apex
Testing & Certification Limited (Apex) was commissioned to undertake the
Environmental Team (ET) services (including environmental monitoring and audit
(EM&A)) for the construction activities in Zone 2A, consisting of Foundation,
Excavation and Lateral Support Works for Integrated Basement and Underground
Road (Contract No.: GW/2020/05/073) ; and Zone 2B & 2C consisting of
Piling Works for Integrated Basement and Underground Road (Contract No.:
CC/2020/2B/088) at WKCD. The purpose of the development in Zone 2A and Zone 2B
& 2C is to reserve for Integrated Basement (IB) and Underground Road (UR).
The Zone 2A construction activities involve the foundation, excavation and
lateral support (ELS) works, road works, drainage diversion works, and
temporary car parking. The Zone 2B & 2C construction activities involve the
piling works. The major construction works and EM&A programme for Zone 2A
and Zone 2B & 2C commenced on 03 October 2020 and 30 September 2021
respectively.
The
overall works for the WKCD fall under two separate categories of Designated
Project (DP) of the Environmental Impact Assessment Ordinance (EIAO), namely an
“engineering feasibility study of urban development projects with a study area
covering more than 20 ha or involving a total population of more than 100 000”
(Item 1 of Schedule 3) and “an underpass more than 100m in length under the built
areas” (Item A.9, Part I, Schedule 2). An Environmental Permit No.
EP-453/2013/B (EP) was issued with respect to the “Underpass Road and Austin
Road Flyover Serving the West Kowloon Cultural District” which specifically
includes the abovementioned category of DP under Item A.9, Part I, Schedule 2
of the EIAO. The captioned projects include part of the abovementioned
underpass road located within the site boundary falls under this same category.
The Monthly EM&A Report is prepared in accordance with the Condition 3.4 of the Environmental Permit No. EP-453/2013/B. This Monthly EM&A Report presents the monitoring works at Zone 2A and Zone 2B & 2C from 01 to 31 March 2022. The purpose of this report is to summarise the findings in the EM&A of the project over the reporting period.
The
organisation chart and lines of communication with respect to the on-site
environmental management structure together with the contact information of the
key personnel are shown in Appendix A.
During the reporting period, construction works at Zone 2A undertaken include:
Zone 2A-1
● ELS (Stage 1) – Grouting / Pipe Pile Works
– King Post & Erection of Steel Column for Working Platform
– Stage 2 Grouting
Zone 2A-2
● ELS (Stage 1) – Grouting / Pipe Pile Works
– Pipe Pile Construction
– Stage 2 Grouting
During the reporting period, construction works at Zone 2B & 2C undertaken include:
KD01 (Stage 1-1),
KD05 (Section 1), KD06 (Section 2)
● Bored Pile Works
– Predrilling, RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation
KD02 (Stage 5-1)
● Bored Pile Works
– Airlifting, Cage Installation & Concreting and Excavation
KD03 (Stage 3-1)
– Predrilling
KD07 (Section 3), KD08 (Section 4), KD09 (Section 5)
● Trial Pile Works
– RCD
Drilling, Airlifting, Cage Installation &
Concreting and Excavation
● Bored Pile Works
– Predrilling,
RCD Drilling, Airlifting,
Cage Installation & Concreting and Excavation
The
Construction Works Programme of Zone
2A and Zone 2B & 2C is provided in Appendix B. A
layout plan of the Project is provided in Figure 1. Please refer to Table 4.3 and Table 4.4 on the status of the environmental
licenses.
The EM&A programme requires environmental monitoring of air quality, noise, landscape and visual as specified in the approved EM&A Manual.
A summary of impact EM&A requirements is presented in Table 1.1.
Table 1.1: Summary of Impact EM&A Requirements
Parameters |
Descriptions |
Locations |
Frequencies |
Air Quality |
24-Hours TSP |
AM3-The Victoria Towers Tower 1 |
At least once every 6 days |
1-Hour TSP |
AM3-The Victoria Towers Tower 1 |
At least 3 times every 6 days |
|
24-Hours TSP |
AM4-Canton Road Government Primary School |
At least once every 6 days |
|
1-Hour TSP |
AM4-Canton Road Government Primary School |
At least 3 times every 6 days |
|
24-Hours TSP |
AM5-Topside Developments at West Kowloon Terminus Site |
At least once every 6 days |
|
1-Hour TSP |
AM5-Topside Developments at West Kowloon Terminus Site |
At least 3 times every 6 days |
|
Noise |
Leq, 30 minutes |
NM2-The Arch, Sun Tower |
Weekly |
Leq, 30 minutes |
NM3-The Victoria Towers Tower 1 |
Weekly |
|
Leq, 30 minutes |
NM4-Canton Road Government Primary School |
Weekly |
|
Leq, 30 minutes |
NM5-Development next to Austin Station |
Weekly |
|
Landscape & Visual |
Monitor implementation of proposed mitigation measures during the
construction stage |
As described in Table 9.1 and 9.2 of the EM&A Manual |
Bi-Weekly |
The EM&A
programme for the Project should require 5 noise monitoring station and 5 air
quality monitoring stations located closest to the Project area. With regard to the monitoring activities at M+ Museum and the
Lyric Complex, three monitoring stations had been considered, including AM1
(International Commerce Centre), AM2 (The Harbourside Tower 1) for air
monitoring, and NM1 (The Harbourside Tower 1) for noise monitoring.
In the context of the construction activities in Zone 2A and Zone
2B & 2C, all other monitoring locations including AM3 (The
Victoria Towers Tower 1), AM4 (Canton Road Government Primary School), and AM5 (Topside Developments at West
Kowloon Terminus Site) for air monitoring; and NM2 (The Arch, Sun
Tower), NM3 (The Victoria Towers Tower 1), NM4 (Canton Road Government Primary
School) and NM5 (Development next to Austin Station) for noise monitoring, have been taken into account. However, access to all these
originally designated monitoring stations was declined as described below
point-by-point.
The Arch management office and owners’
committee have formally declined the proposal of setting up noise monitoring
instrument on its premises at the podium level of Sun Tower (NM2) on 24 July
2014. Thus, alternative noise monitoring location was identified
at the ground floor in front of The Arch – Sun Tower (NM2A), which is at the same location as stated in
the EM&A Manual for consistency. No management approval is required at the ground
floor for conducting the noise monitoring. This alternative air
monitoring location was approved by EPD on 29 September 2020.
The Victoria Towers management office
formally declined the proposal of setting up air quality
and noise monitoring instruments on its premises at the podium area of
Tower 1 (AM3/NM3) on 16 June 2020. Alternative air monitoring location was
identified at ground floor at the Northeast corner of West Kowloon Station’s
station box (AM3A), in the same direction to the area of major construction
site activities in Zone 2A. This alternative air monitoring location was
approved by EPD on 29 September 2020. An alternative noise monitoring location
was identified at the ground floor in front of the Xiqu Centre (NM3A), which is
set closer to the construction site boundary with more direct line sight to the
major site activities and higher exposure to the construction noise with no
disturbance to the premises’ occupants during noise monitoring activities. No
management approval is required at the ground floor for conducting the noise
monitoring. This alternative air monitoring location was approved by EPD on 29
September 2020.
Canton Road Government Primary School formally
declined the proposal of setting up air quality and
noise monitoring instruments on
its premise at the podium level (AM4/NM4) on 16 June 2020. Alternative air monitoring location was
identified at ground floor at the Southeast
corner of West Kowloon Station’s station box (AM4A), in same
direction to the area of major construction site activities in Zone 2A. This
alternative air monitoring location was approved by EPD on 29 September 2020. An
alternative noise monitoring location was identified at the ground floor next
to Tsim Sha Tsui Fire Station (NM4A), which is set
closer to the construction site boundary with more direct line sight to the
major site activities and higher exposure to the construction noise with no
disturbance to the premises’ occupants during noise
monitoring activities. No management approval is required at the ground floor
for conducting the noise monitoring. This alternative air monitoring location
was approved by EPD on 29 September 2020.
MTR also formally declined the access to the
designated AM5 location (topside developments at West Kowloon Terminus Site) on
15 July 2020. Alternative air monitoring location was identified at ground
floor at the North of West
Kowloon Station’s station box (AM5A), in same direction to the area of
major construction site activities in Zone 2A. This alternative air monitoring
location was approved by EPD on 29 September 2020.
Grand Austin property management office formally
declined our proposal of setting up noise monitoring instrument on
its premises at the podium level (NM5) on 10 July 2020. Alternative noise
monitoring location was identified at the Pedestrian road (ground floor)
outside West Kowloon Station (NM5A),
which is set closer to the construction site boundary with more direct line
sight to the major site activities and higher exposure to the construction
noise with no disturbance to the premises’ occupants during noise monitoring
activities. No management approval is required at the ground floor for conducting
the noise monitoring. This alternative air monitoring location was approved by
EPD on 29 September 2020.
The Environmental Quality Performance Limits for air quality and noise are shown in Appendix C.
The Event and Action Plan for air quality, construction noise, and landscape and visual are shown in Appendix D.
The EM&A programme followed the
recommended mitigation measures in the EM&A Manual. The EM&A
requirements as well as the summary of implementation status of the
environmental mitigation measures are provided in Appendix J.
Air quality and noise monitoring methodology,
including the monitoring locations, equipment used, parameters, frequency and
duration etc., are described in this Section. The environmental monitoring
schedules for the reporting period and the tentative monitoring Schedule for
the coming month are provided in Appendix
E.
The relevant EM&A monitoring requirements
and details for landscape and audit impact, are also presented in this Section.
Table 2.1 summarizes the monitoring parameters,
frequency and duration of the TSP monitoring.
Table 2.1: Air Quality
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency |
Duration |
24-hour
TSP |
At
least once in every six-days |
24
hours |
1-hour
TSP |
At
least 3 times every six-days |
60
minutes |
Monitoring
stations and locations are given in Table 2.2 and
shown in Figure
1.
Table 2.2: Air Quality Monitoring Station
Monitoring
Station |
Location
Description |
AM3A |
Northeast
corner of West Kowloon Station’s station box (G/F) |
AM4A |
Southeast
corner of West Kowloon Station’s station box (G/F) |
AM5A |
North
of West Kowloon Station’s station box (G/F) |
Continuous 24-hour TSP air quality monitoring was conducted using High Volume Sampler (HVS) (Model: TE-5170) located at the designated monitoring station. The HVS meets all the requirements stated in of the EM&A Manual. Portable direct reading dust meter was used to carry out the 1-hour TSP monitoring. Table 2.3 summarizes the equipment used in the impact air quality monitoring. Copies of the calibration certificates for the HVS, calibration kit and portable dust meters are attached in Appendix F.
Table 2.3: TSP Monitoring
Equipment
Equipment |
Model |
24-hour TSP monitoring |
|
High
Volume Sampler |
TE-5170
(Serial No.: 4340;
3998; 4344) |
Calibrator |
TE-5025A
(Orifice I.D.: 3543) |
1-hour
TSP monitoring |
|
Portable
direct reading dust meter |
Sibata
LD-3B (Serial No.: 235811, 336338, 567188) |
Calibration of the HVS (five-point calibration) using
Calibration Kit was carried out every two months. The HVS calibration orifice
will be calibrated annually. Calibration certificate of the TE-5025A
Calibration Kit and the HVS are provided in Appendix
F.
The 1-hour TSP monitoring should be determined periodically (e.g. annually) by the HVS to check the validity and accuracy of the results measured by direct reading method.
24-hour
TSP Monitoring
Installation
The HVS was installed at the site boundary. The following criteria were considered in the installation of the HVS.
– A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
– The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
– A minimum of 2 metres separation from walls, parapets and penthouse was required for rooftop sampler.
– A minimum of 2 metres separation from any supporting structure, measured horizontally was required.
– No furnace or incinerator flues or building vent were nearby.
– Airflow around the sampler was unrestricted.
– The sampler has been more than 20 metres from any drip line.
– Permission was obtained to set up the sampler and to obtain access to the monitoring station.
– A secured supply of electricity is needed to operate the sampler.
Preparation of Filter Papers
– Glass fibre filters were labelled and sufficient filters that were clean and without pinholes were selected.
– The filters used are specified to have a minimum collection efficiency of 99 percent for 0.3 µm (DOP) particles.
– All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C with relative humidity (RH) < 50% and was not variable by more than ±5 %. A convenient working RH was 40%. All preparation of filters was done by Hong Kong Laboratory Accreditation Scheme (HOKLAS) accredited laboratory.
Field Monitoring Procedures
– The power supply was checked to ensure the HVS works properly.
– The filter holder and the area surrounding the filter were cleaned.
– The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
– The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
– The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to avoid air leakage at the edges.
– The shelter lid was closed and was secured with the aluminium strip.
– The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
– A new flow rate record sheet was set into the flow recorder.
– The flow rate of the HVS was checked and adjusted at around 1.3 m3/min. The range specified in the EM&A Manual was between 0.6-1.7 m3/min.
– The programmable timer was set for a sampling period of 24 hours, and the starting time, weather condition and the filter number were recorded.
– The initial elapsed time was recorded.
– At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
– It was then placed in a clean plastic envelope and sealed.
– All monitoring information was recorded on a standard data sheet.
– Filters were sent to a Hong Kong Laboratory Accreditation Scheme (HOKLAS) accredited laboratory for analysis.
Maintenance and Calibration
– The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
– HVSs were calibrated upon installation and thereafter at bi-monthly intervals. The calibration kits were calibrated annually.
– Calibration records for HVS and calibration kit are shown in Appendix F.
1-hour
TSP Monitoring
Field Monitoring
The
measuring procedures of the 1-hour dust meter are in accordance with the
Manufacturer’s Instruction Manual as follows:
– Turn the power on.
– Close the air collecting opening cover.
– Push the “TIME SETTING” switch to [BG].
– Push “START/STOP” switch to perform background measurement for 6 seconds.
– Turn the knob at SENSI ADJ position to insert the light scattering plate.
– Leave the equipment for 1 minute upon “SPAN CHECK” is indicated in the display.
– Push “START/STOP” switch to perform automatic sensitivity adjustment. This measurement takes 1 minute.
– Pull out the knob and return it to MEASURE position.
– Setting time period of 1 hour for the 1-hour TSP measurement.
– Push “START/STOP” to start the 1-hour TSP measurement.
– Regular checking of the time period setting to ensure monitoring time of 1 hour.
Maintenance and
Calibration
– The 1-hour dust meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality monitoring.
– Calibration records for direct dust meters are shown in Appendix F.
Weather Condition
– Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix H.
Table 2.4 summarizes the monitoring parameters,
frequency and duration of noise monitoring. The noise in A-weighted levels Leq,
L10 and L90 are recorded in a 30-minute interval between
0700 and 1900 hours.
Table 2.4: Noise Monitoring Parameters, Period and Frequency
Time Period |
Parameters |
Frequency |
Daytime on normal weekdays (0700-1900 hours) |
Leq(30 min), L90(30
min) & L10(30 min) |
Once every week |
Note: *70 dB(A) for schools and 65 dB(A) during school examination
periods.
If works are to be carried out during restricted hours, the conditions
stipulated in the Construction Noise Permit (CNP) issued by the Noise Control
Authority have to be followed.
Noise monitoring stations and locations are given in Table 2.5 and shown in Figure 1.
Table 2.5: Noise Monitoring Station
Monitoring Station |
Location |
NM2A |
|
NM3A |
|
NM4A |
Next to Tsim Sha Tsui Fire Station (G/F) |
NM5A |
Pedestrian road (G/F) outside West Kowloon Station |
Integrating Sound Level Meter was used for noise monitoring. It was a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (LAeq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 2.6 summarizes the noise monitoring equipment model being used.
Table 2.6: Noise Monitoring Equipment
Equipment Model |
|
Integrating Sound Level Meter |
Calibrator |
AWA5661 (Serial No.: 301135)
|
Pulsar 100B (Serial No.: 039507) |
Field
Monitoring
– The microphone of the Sound Level Meter was set at least 1.2 m above the ground.
– Free Field measurement was made at NM5A monitoring location.
– The battery condition was checked to ensure the correct functioning of the meter.
– Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 30 minutes intervals (between 0700-1900 on normal weekdays)
– Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1 kHz. If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid and has to be repeated after re-calibration or repair of the equipment.
– During the monitoring period, the Leq, L10 and L90 were recorded. In addition, any site observations and noise sources were recorded on a standard record sheet.
– A correction of +3dB(A) was made to the free field measurements.
Maintenance
and Calibration
– The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.
– The sound level meter and calibrator are sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
– Calibration records are shown in Appendix F.
Weather
Condition
– Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix H.
Table 2.7 details the monitoring program (as proposed in the WKCD EIA report) for landscape and visual impact during the construction phase.
Table 2.7: Monitoring Program for Landscape and Visual Impact during Construction Phase
Stage |
Monitoring Task |
Frequency |
Report |
Approval |
Construction |
Monitor implementation of proposed mitigation measures during the
construction stage. |
Bi-weekly |
ET to report on Contractor’s compliance |
Counter-signed by IEC |
During the landscape and visual impact monitoring, any changes in relation to the landscape and visual amenity should be monitored with reference to the baseline conditions of the site. In addition, mitigation measures were proposed in the WKCD EIA report to minimise the landscape and visual impacts during the construction phase. The proposed mitigation measures as shown in Table 9.1 and Table 9.2 of the EM&A Manual should be checked for proper implementation.
Air quality, noise and
landscape and visual impact monitoring
was undertaken in compliance with the
EM&A Manual during the reporting month.
Results of 1-hour TSP are summarised in Table 3.1. Graphical plots of the monitoring results are shown in Appendix G.
Table 3.1: Summary
of 1-hour TSP monitoring results
Monitoring Station |
Monitoring Date |
Start Time |
1-hour TSP (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
||
1st Result |
2nd Result |
3rd Result |
||||||
AM3A |
04-Mar-22 |
14:09 |
56 |
57 |
55 |
36-64 |
280.4 |
500 |
10-Mar-22 |
08:02 |
53 |
61 |
55 |
||||
16-Mar-22 |
14:18 |
62 |
62 |
55 |
||||
22-Mar-22 |
08:07 |
62 |
64 |
60 |
||||
28-Mar-22 |
14:01 |
42 |
36 |
36 |
||||
AM4A |
04-Mar-22 |
14:17 |
56 |
58 |
56 |
42-67 |
278.5 |
500 |
10-Mar-22 |
08:10 |
57 |
59 |
52 |
||||
16-Mar-22 |
14:26 |
57 |
60 |
61 |
||||
22-Mar-22 |
08:15 |
59 |
67 |
66 |
||||
28-Mar-22 |
14:09 |
44 |
42 |
43 |
||||
AM5A |
04-Mar-22 |
14:32 |
54 |
56 |
56 |
41-68 |
275.4 |
500 |
10-Mar-22 |
08:27 |
60 |
57 |
55 |
||||
16-Mar-22 |
14:41 |
60 |
55 |
56 |
||||
22-Mar-22 |
08:32 |
68 |
66 |
65 |
||||
28-Mar-22 |
14:24 |
42 |
41 |
43 |
Results of 24-hour TSP are summarised in Table 3.2. Graphical plots of the monitoring results are shown in Appendix G.
Table 3.2: Summary
of 24-hour TSP monitoring results
Monitoring Station |
Monitoring Date |
Start Time |
Monitoring Results (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
AM3A |
04-Mar-22 |
10:00 |
54.0 |
39.9-58.1 |
152.4 |
260 |
10-Mar-22 |
10:00 |
49.1 |
||||
16-Mar-22 |
10:00 |
52.5 |
||||
22-Mar-22 |
10:00 |
58.1 |
||||
28-Mar-22 |
10:00 |
39.9 |
||||
AM4A |
04-Mar-22 |
10:00 |
56.8 |
42.6-58.5 |
152.6 |
260 |
10-Mar-22 |
10:00 |
54.9 |
||||
16-Mar-22 |
10:00 |
55.9 |
||||
22-Mar-22 |
10:00 |
58.5 |
||||
28-Mar-22 |
10:00 |
42.6 |
||||
AM5A |
04-Mar-22 |
10:00 |
55.0 |
41.9-60.7 |
141.1 |
260 |
10-Mar-22 |
10:00 |
53.8 |
||||
16-Mar-22 |
10:00 |
56.7 |
||||
22-Mar-22 |
10:00 |
60.7 |
||||
28-Mar-22 |
10:00 |
41.9 |
No exceedance of 1-hour and 24-hour TSP (Action or Limit Level) was recorded in the reporting period.
The construction noise monitoring results are summarized in Table 3.3. Graphical plots of the monitoring data and the station set-up as façade and free-field measurements are shown in Appendix G.
Table 3.3: Summary
of noise monitoring results during normal weekdays
Monitoring Stations |
Monitoring Date |
Start Time |
End Time |
Leq
(30 mins) dB(A) |
Limit Level for Leq (dB(A)) |
NM2A |
04-Mar-22 |
14:39 |
15:09 |
59.8 |
75 |
10-Mar-22 |
08:32 |
09:02 |
59.9 |
||
16-Mar-22 |
14:48 |
15:18 |
60.2 |
||
22-Mar-22 |
08:37 |
09:07 |
59.7 |
||
28-Mar-22 |
14:31 |
15:01 |
59.5 |
||
NM3A |
04-Mar-22 |
16:09 |
16:39 |
70.1 |
75 |
10-Mar-22 |
10:05 |
10:35 |
69.6 |
||
16-Mar-22 |
16:18 |
16:48 |
69.8 |
||
22-Mar-22 |
10:10 |
10:40 |
69.6 |
||
28-Mar-22 |
16:01 |
16:31 |
69.2 |
||
NM4A |
04-Mar-22 |
16:44 |
17:14 |
67.8 |
70/65^# |
10-Mar-22 |
10:40 |
11:10 |
68.1 |
||
16-Mar-22 |
16:53 |
17:23 |
68.0 |
||
22-Mar-22 |
10:45 |
11:15 |
67.9 |
||
28-Mar-22 |
16:36 |
17:06 |
68.3 |
||
NM5A* |
04-Mar-22 |
15:29 |
15:59 |
65.8 |
75 |
10-Mar-22 |
09:24 |
09:54 |
66.0 |
||
16-Mar-22 |
15:38 |
16:08 |
65.7 |
||
22-Mar-22 |
09:29 |
09:59 |
66.1 |
||
28-Mar-22 |
15:21 |
15:51 |
65.8 |
Remarks: * +3dB (A) correction was applied to free-field measurement. ^ 70 dB(A) for
schools and 65 dB(A) during school examination periods. # No
school examination
was conducted in the reporting period. |
Two Action Level exceedances due to two complaints with no Limit Level
exceedance of construction noise was recorded in the reporting month.
Construction works
were extended to 1900-2300 hours on 01 to 05, 07 to 12, 14 to 19, 21 to 25 and 28
to 31 March 2022; and to holidays 0900-1800 hours on 20 and 27 March 2022. In
accordance with the EM&A Manual, additional monitoring was carried out
during the restricted hours on 04, 10, 16, 20, 22, 27 and 28 March 2022. The Leq
(5 mins) is in the range of 57.1-66.8 dB(A). Construction Noise Permits for the
works carried out during restricted hours were obtained and listed in Table 4.3 and
Table 4.4.
Landscape and visual impact inspections were conducted as part of the weekly site inspections on 10 and 24 March 2022 for Zone 2A and 08 and 22 March 2022 for Zone 2B & 2C during the reporting month. As reviewed by the registered Landscape Architect, no adverse comment on landscape and visual aspects was made during these inspections.
The landscape and visual mitigation measures were implemented during the reporting period. The summary of implementation status of the environmental mitigation measures is provided in Appendix J.
Construction
phase weekly site inspections were carried out on 03, 10, 17, 24 and 31 March
2022 at Zone 2A. The joint site inspection with IEC, ET,
ER and Contractor for Zone 2A was held on 17 March 2022. All observations
have been recorded in the site inspection checklist and passed to the
Contractor together with the appropriate recommended mitigation measures where
necessary.
The key observations from the site inspections and associated
recommendations are summarized in Table 4.1.
Table 4.1: Summary
of Site Inspections and Recommendations for Zone 2A
Inspection Date |
Parameter |
Observation / Recommendation |
Contactor’s Responses /
Action(s) Undertaken |
Close-out (Date) |
03-Mar-22 |
Water
Quality |
The contractor was reminded that the idle
stockpile shall be fully covered with tarpaulin. |
The contractor has fully covered the idle
stockpile with tarpaulin. |
03-Mar-22 |
03-Mar-22 |
Water
Quality |
The contractor was reminded to pump out water in
u-channel regularly to maintain proper function and efficient
operation. |
The contractor has pumped out the water in
u-channel. |
04-Mar-22 |
17-Mar-22 |
Waste |
The contractor has sorted and removed the waste
from site. |
19-Mar-22 |
|
17-Mar-22 |
Air
Quality |
The contractor was reminded to replace the NRMM
label with proper colour on the PME (at the seaside) |
The contractor has replaced the NRMM label with
proper colour on the PME (at the seaside) |
18-Mar-22 |
24-Mar-22 |
Water
Quality |
The contractor was reminded that the site
entrance shall maintain cleaned to avoid muddy water spread on the public
road. |
The contractor has provided regular cleaning at
site entrance to avoid muddy water spread on public road. |
25-Mar-22 |
Construction phase weekly site inspections
were carried out on 01, 08, 15, 22 and 29 March 2022 at Zone 2B & 2C. The
joint site inspection with IEC, ET, ER and Contractor for Zone 2B & 2C was
held on 15 March 2022. All observations have been recorded in the site
inspection checklist and passed to the Contractor together with the appropriate
recommended mitigation measures where necessary.
EPD inspection was conducted on 29 March
2022 at Zone 2B & 2C. No adverse comments or prosecution was given. EPD
inspector has inspected the condition of main entrance, wheel washing
facilities, water treatment facilities, water barriers near coast, outlet of
DN1350 pipeline and the noise mitigation on site. The EPD inspector remined the
Contractor to keep monitor the condition of the public road and strengthen the
road clean work. Also, the EPD inspector remined the Contractor be caution of
the runoff control as the rain season is coming, make sure the site has enough
storage capacity for the runoff, and ensure the water barriers at the coast is
well maintained.
The key observations
from the site inspections and associated recommendations are summarized in Table 4.2.
Table 4.2: Summary
of Site Inspections and Recommendations for Zone 2B & 2C
Inspection
Date |
Parameter |
Observation
/ Recommendation |
Contactor’s
Responses / Action(s) Undertaken |
Close-out
(Date) |
01-Mar-22 |
Noise impact |
The contractor
was reminded to properly set up the noise barriers to minimize noise impact. |
The contractor
has properly set up the noise barriers to minimize noise impact. |
02-Mar-22 |
01-Mar-22 |
Water Quality |
The contractor
was reminded that the idle stockpile shall be fully covered with tarpaulin or
removed. |
The contractor
has removed the idle stockpile. |
02-Mar-22 |
08-Mar-22 |
Water Quality |
The contractor
was reminded that stockpiles of cement shall be fully covered when not being
used. |
The contractor
has fully covered the stockpiles of cement. |
09-Mar-22 |
08-Mar-22 |
Waste Management |
The contractor
was reminded to properly place the chemicals with drip trays/remove to
storage area to prevent chemical spillage. |
The contractor
has removed the chemicals to chemical storage to prevent chemical spillage. |
09-Mar-22 |
15-Mar-22 |
Air Quality |
The contractor
was reminded to increase the wate spraying frequently to minimize dust
impact. |
The contractor
has increased the water spraying frequently to minimize dust impact. |
16-Mar-22 |
15-Mar-22 |
Water Quality |
The contractor
was reminded that the idle stockpile shall be fully covered with tarpaulin or
removed. |
The contractor
has removed the idle stockpile. |
16-Mar-22 |
22-Mar-22 |
Water Quality |
The contractor
was reminded to provided the concrete bound at the seafront to prevent muddy
water leakage. |
The contractor
has provided the concrete bound at the seafront to prevent muddy water
leakage. |
25-Mar-22 |
29-Mar-22 |
Water Quality |
The contractor
was reminded that sandbags shall be provided on site to direct storm water. |
The contractor
has provided sandbags on site to direct storm water. |
30-Mar-22 |
The Contractors have been registered as a
chemical waste producer for the Project. Construction and demolition (C&D)
material sorting will be carried out on site. A sufficient number of
receptacles were available for general refuse collection.
As advised by the Zone 2A Contractor, 21.02 tonnes, 318.10 tonnes and
1543.51 tonnes of inert C&D material were disposed of as public fill to
Chai Wan Public Fill Barging Point, Tseung Kwan O Area 137 Public Fill and Tuen
Mun Area 38 Public Fill respectively, while 10.92 tonnes of general refuse were
disposed of at SENT landfill respectively. 4.47 tonnes of metals, 0.0 tonne of
paper/cardboard packaging, 0.0 tonne of plastics and 0.0 tonne of timber was
collected by recycling contractors in the reporting month. 0.0 tonnes of inert
C&D material was reused on site. 487.20 tonnes of inert C&D material
were reused in other projects and 0.0 tonne of inert C&D material was
imported for reuse at site in the reporting month. 0.0 tonne of inert C&D
material was disposed to sorting facility and 0.0 tonne of chemical waste was
collected by licensed contractors in the reporting period.
As advised by the
Zone 2B & 2C Contractor, 4926.22 tonnes and 5953.37 tonnes of inert C&D
material were disposed of as public fill to Tseung Kwan O Area 137 Public Fill
and Tuen Mun Area 38 Public Fill respectively, while 16.15 tonnes of general
refuse were disposed of at SENT landfill. 00.00 tonne of metals, 0.0 tonne of
paper/cardboard packaging, 0.0 tonne of plastics and 0.0 tonne of timber was
collected by recycling contractors in the reporting month. 2176.32 tonnes of
inert C&D material were reused on site. 11721.21 tonnes of inert C&D
material were reused in other projects and 0.0 tonne of inert C&D material
was imported for reuse at site in the reporting month. 0.0 tonne of inert
C&D material was disposed to sorting facility and 1.40
tonne of chemical waste was collected by licensed contractors in the reporting
period.
The cumulative waste generation records for
Zone 2A and Zone 2B & 2C are shown in Appendix I.
The environmental permits, licenses, and/or
notifications on environmental protection for this Project which were valid
during the period are
summarised in Table 4.3.
Table 4.3: Status
of Environmental Submissions, Licenses and Permits for Zone 2A
Permit /
License No. / Notification
/ Reference
No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Chemical
Waste Producer Registration |
||||
WPN5113-256-B2597-01 |
10-Sep-20 |
-- |
Valid |
-- |
Billing
Account Construction Waste Disposal |
||||
7037500 |
09-Jun-20 |
-- |
Account Active |
-- |
Construction
Noise Permit |
||||
GW-RE-0096-22 |
11-Feb-22 |
10-May-22 |
Valid |
Piling Works |
Wastewater
Discharge License |
||||
WT00037344-2021 |
01-Feb-21 |
28-Feb-26 |
Valid |
-- |
Notification
under Air Pollution Control (Construction Dust) Regulation |
||||
456376 |
21-May-20 |
-- |
Notified |
-- |
The environmental permits, licenses, and/or
notifications on environmental protection for this Project which were valid
during the period are
summarised in Table 4.4.
Table 4.4: Status
of Environmental Submissions, Licenses and Permits for Zone 2B & 2C
Permit / License No. / Notification / Reference No. |
Valid
Period |
Status |
Remarks |
|
From |
To |
|||
Chemical
Waste Producer Registration |
||||
WPN5113-256-V2302-01 |
17-Aug-21 |
-- |
Valid |
-- |
Billing
Account Construction Waste Disposal |
||||
7041264 |
11-Aug-21 |
-- |
Account Active |
-- |
Construction
Noise Permit |
||||
GW-RE0148-22 |
22-Feb-22 |
21-May-22 |
Valid |
-- |
Wastewater
Discharge License |
||||
WT00039734-2021 |
25-Nov-21 |
30-Nov-26 |
Valid |
-- |
Notification
under Air Pollution Control (Construction Dust) Regulation |
||||
470022 |
29-Jul-21 |
-- |
Notified |
-- |
The EM&A programme followed the
recommended mitigation measures in the EM&A Manual. The EM&A
requirements as well as the summary of implementation status of the
environmental mitigation measures are provided in Appendix J. In particular, the following mitigation measures were brought to
attention during the site inspections:
Air
Quality
– Regular
checking shall provided to ensure the NRMM label on PME was placed with proper
colour.
Temporary
Water Drainage System & Water Quality
– Idle stockpile should be fully covered with
tarpaulin when not being used or removed from the site.
– Water in u-channel shall be cleaned regularly
to maintain proper function and efficient
operation.
– Regular cleaning shall provided at site
entrance to avoid muddy water spread on public road.
Waste
Management
– Sorting of
C&D material shall carry out to recover any recycle portion.
– Water spraying frequency shall be increased to minimize
dust impact.
Noise
Impact
– Noise barriers
should be properly set up to minimize Noise impact to NSRs.
Waste Management
–
Chemical wastes should
be properly placed with drip trays/removed to storage area to prevent chemical spillage.
Water
Quality
– Idle stockpile of dusty materials should be
fully covered with tarpaulin when not being used or removed from the site.
– Concrete bound
shall be provided at the seafront to prevent muddy water leakage.
– Sandbags shall
be provided on site to direct storm water.
The status
of the required submission under the EP during the reporting period is
summarized in Table 5.1.
Table 5.1: Status of Submissions under the Environmental Permit
EP Condition |
Submission |
Submission Date |
Condition 3.4 |
Monthly
EM&A Report for February 2022 |
14 March 2022 |
There was no breach of Action or Limit Levels for Air Quality (1-hour TSP and 24-hour TSP) in the reporting month.
Two Action Level exceedances due to two complaints with no Limit Level exceedance of construction noise was recorded in the reporting month.
Five environmental
complaints were received in the reporting month.
On 1 March 2022, WKCDA has received a complaint from EPD. Referring to
the photo provided by the complainant, feculent water was spotted in the
waterbody of Victoria Harbour near WKCD construction site on 1 March 2022. Investigation revealed that, feculent
water was observed near the coastal area of Zone 2B & 2C site on 1 March
2022. After investigation, there was no identified source of wastewater leakage
from Zone 2 sites into the waterbody of Victoria Harbor. In addition, good
effluent quality has been properly maintained on both sites. Thereby, the
complaint might not be attributable to Zone 2 sites. Nonetheless, the
Contractors are recommended to strictly maintain good site practices to avoid
wastewater flowing into to the waterbody of Victoria Harbor.
On 2 March 2022, a noise-related complaint was received from the
security control room of The Arch through the WKCD Hotline and the case was
referred by WKCDA on 2 March 2022. The complainant (a resident from The Arch)
claimed that construction noise was from WKCD construction site next to M+ and
opposite to the Harbourside in the early morning. As per the complainant, the
construction work used to start after 9am, but recently the noise started at
around 7am from 28 February to 2 March 2022. which caused disturbance. The
complainant also enquired about the schedule of the construction. Investigation
revealed that no noisy construction work was conducted before 9:00am on WKCD
Zone 2A site at the concerned period. The identified construction noise source
at 7:00am on 28 February to 02 March 2022 might possibly due to site
preparation for concreting and air-lifting activities over 7:00am-7:30am on
WKCD Zone 2B & 2C site. The complaint might be possibly attributable to
Zone 2B & 2C site. Accordingly, in addition to existing noise mitigation
measures (which have been properly maintained daily on site), prompt actions
have been taken (after notification of the complaint) to enhance the noise
barriers in order to minimize the noise. Moreover, noise measurement and
monitoring were carried out with no exceedance. Nonetheless, the Contractors
are reminded and recommended to avoid noisy works before 9am, maintain good
practices on site, and strengthen the implementation of noise mitigation
measures to reduce impact to the nearby neighbors. Main contractors will carry
out inspection and close supervision to ensure noise mitigation measures had
been implemented.
On 11 March 2022, WKCDA has received a noise-related complaint referred
by EPD. On 11 March 2022, EPD has received a complaint referred by Mr. Hung,
member of Yau Tsim Mong District Council (YTMDC). YTMDC has recently received a
complaint from a resident who lived near Kowloon Station and expressed concern
about noise disturbance in high frequency was being generated from WKCD
construction site for consecutive Sundays. Mr. Hung has requested WKCD
construction sites to provide noise monitoring data and ensure work procedure
is complied with environmental protection regulations. In addition, he has
reminded WKCDA and the Contractors not to conduct noisy works or generate noise
disturbance to the neighborhood on Sundays in the future. On 15 March 2022,
additional information was received from the same complainant, claiming that
construction activity was observed in WKCD construction sites near which
generated construction noise on 13 March 2022. The complainant expressed
concern about noise disturbance to the nearby resident and noise mitigation
measures on site
Investigation revealed that some noise emissions on Sundays in February
2022 might possibly due to the construction activities carried out on WKCD Zone
2B & 2C site on Sundays 13 and 27 February 2022. Therefore, the noise
source on 13 and 27 February 2022 might be possibly attributable to Zone 2B
& 2C site. However, no construction work was conducted on Zone 2B & 2C
site on 06 and 13 March 2022 (only one generator was used). In addition, the
site activities on 13 February 2022 were in compliance with the permitted
working hours (09:00-23:00) in accordance with the CNP No: GW-RE1288-21 (of
which one unit of water pump, one unit of generator, one unit of RCD, one unit
of power pack and one unit of air compressor were used from PME Group F).The
site activities on 27 February 2022 were in compliance with the permitted
working hours (09:00-23:00) in accordance with the CNP No: GW-RE0148-22 (of
which one unit of water pump, one unit of generator, one unit of RCD, one unit
of power pack and one unit of air compressor were used from PME Group G). The
air compressor and generator are labelled as QPME by EPD. No construction work
was undertaken on recent Sundays on WKCD Zone 2A site over the concerned
period. Noise mitigation measures have already been implemented and maintained
on both Zone 2A and 2B & 2C sites. Moreover, noise measurement and
monitoring were carried out with no exceedance. Nonetheless, the Contractors
are reminded maintain good practices on site, and strengthen the implementation
of noise mitigation measures to reduce impact to the nearby neighbors. On the
other hand, construction works not related to WKCD project were observed close
to the noise sensitive receivers nearby the Austin Road Flyover on 13 March
2022. These activities might be possibly the noise source identified by the
complainant on 13 March 2022.
On 21 March 2022, WKCDA has received a complaint referred by EPD
regarding dust emission generated from WKCD construction site. On 11 March
2022, the complainant has expressed concern of construction sand and rock on
the ground without proper dust mitigation measures near M+ Construction Site
(opposite to The Arch), which has caused damage to the private car.
Investigation revealed that there was no finding of dust pollution from
WKCD-Zone 2A and 2B & 2C sites on 11 March 2022. However, some sand on
public road might possibly due to WKCD Zone 2B & 2C site activities.
Thereby, the identified sand on public road might be attributable to Zone 2B
& 2C site activities. In response, prompt actions have been taken to clean
the public road in addition to existing mitigation measures mitigation measures
on Zone 2B & 2C site (wheel washing, on-site dust suppression, regular
removal of sand from the public road at the boundary of Zone 2B & 2C site).
Moreover, dust monitoring is regularly conducted at the site boundary with no
exceedance. Nonetheless, the Contractors are recommended to maintain good
practice on site, and strengthen the implementation of mitigation measures to
reduce impacts to the nearby neighbors.
On 21 March 2022, WKCDA has also received a complaint referred by EPD
regarding construction dust pollution and muddy water discharge generated from
WKCD construction site. On the 21 March 2022, the complainant has expressed
concern of muddy water and sand flow into public road without proper mitigation
measures near WKCD Construction Site, seriously affecting the environment and
requested findings from EPD. Investigation revealed that, there was no dust
pollution or muddy water discharge from Zone 2A and 2B & 2C sites. However,
some sand on the nearby public road might possibly due to Zone 2B & 2C site
activities. Thereby, observed sand on the public road (by the complainant)
might be attributable to Zone 2B & 2C site activities. In response, prompt
actions have been taken by the Contractor to clean the public road in addition
to existing migration measures (dust control, wheel washing, regular cleaning
of sand from the public road at the site boundary, sealing of the bottom of
site hoarding with concrete) to avoid disturbance to the public. Dust
monitoring is also regularly conducted at the site boundary with no exceedance.
Nonetheless, the Contractors are recommended to maintain good practice on site,
and strengthen the implementation of dust water control measures to reduce impacts
to the nearby neighbors.
The cumulative statistics on complaints were provided in Appendix K.
No notifications of summons or successful prosecutions were received this month. The cumulative statistics on notifications of summons and successful prosecutions were provided in Appendix K.
The major site works for
Zone 2A scheduled to be commissioned in the coming month include:
Zone 2A-1
● ELS (Stage 1) – Grouting / Pipe Pile Works
– King Post & Erection of Steel Column for Working Platform
– Stage 2 Grouting
– Pumping Test
Zone 2A-2
● ELS (Stage 1) – Grouting / Pipe Pile Works
– King Post & Erection of Steel Column for Working Platform
– Pipe Pile Construction
– Stage 2 Grouting
The major site works for Zone 2B & 2C
scheduled to be commissioned in the coming month include:
KD01 (Stage 1-1), KD05 (Section 1), KD06 (Section 2)
● Bored Pile Works
– Predrilling, RCD Drilling, Airlifting, Cage Installation & Concreting and Excavation
KD02 (Stage 5-1)
● Bored Pile Works
– Airlifting, Cage Installation & Concreting and Excavation
KD03 (Stage 3-1)
– Predrilling
KD07
(Section 3), KD08 (Section 4), KD09 (Section 5)
● Trial Pile Works
– RCD
Drilling, Airlifting, Cage Installation &
Concreting and Excavation
● Bored Pile Works
– Predrilling,
RCD Drilling, Airlifting, Cage Installation &
Concreting and Excavation
Key issues to be considered in the coming
month include:
●
Generation
of dust from construction works;
●
Noise
impact from piling works;
●
Generation
of site surface runoffs and wastewater from activities on-site;
● The temporary drainage system should be well
managed and updated with the site condition, particularly on rainy days;
● Management of stockpiles and slopes,
particularly on rainy days;
● Management of chemicals and avoidance of oil
spillage on-site.
● Sorting, recycling, storage and disposal of
general refuse and construction waste; and
Key issues to be considered in the coming
month include:
● Generation of dust from construction works;
● Noise impact from piling works;
● Generation of site surface runoffs and
wastewater from activities on-site;
● Management of stockpiles and slopes,
particularly on rainy days;
● Sorting, recycling, storage and disposal of
general refuse and construction waste; and
● Management of chemicals and avoidance of oil
spillage on-site.
The environmental site inspection and environmental monitoring will be continued in the coming month. Impact monitoring for air quality and noise for Zone 2A and Zone 2B & 2C in accordance with the approved EM&A Manual has commenced since 03 October 2020 and 30 September 2021 respectively. The tentative monitoring schedule for the coming month is shown in the Appendix E.
The EM&A programme as recommended in the EM&A Manual has been undertaken with the commencement of the construction activities at Zone 2A on 03 October 2020, and the major construction works of Zone 2B & 2C commenced on 30 September 2021.
Monitoring
of air quality and noise with respect to the Projects is underway. In particular, the 1-hour TSP, 24-hour TSP, noise level
(as Leq, 30 minutes) under monitoring have been checked against
established Action and Limit levels. There was no breach of Action or Limit levels
for Air Quality (1-hour TSP and 24-hour TSP) in this reporting month. Two Action Level exceedances due to Two complaints with no Limit Level
exceedance of Construction Noise was recorded in the reporting month.
Five environmental complaints were
recorded in the reporting month. No notifications of summons or successful prosecutions were
received during the reporting month.
Weekly
construction phase site inspections and bi-weekly landscape and visual impact
inspections were conducted during the reporting month as required. It was
observed that the Contractors had implemented all possible and feasible
mitigation measures to mitigate the potential environmental impacts during
construction phase works.
Potential environmental impacts due to the
construction activities, including air quality, noise, water quality, waste, landscape and visual, will be
monitored or reviewed. The recommended environmental mitigation measures shall be implemented on site and regular
inspections as required will be carried out to ensure that the environmental conditions are acceptable.