Contents

Executive summary

1       Introduction

1.1      Background

1.2      Project Organisation

1.3      Environmental Status in the Reporting Period

2       Summary of EM&A Requirements and Mitigation Measures

2.1      Monitoring Requirements

2.2      Environmental Mitigation Measures

3       Summary of EM&A Results

3.1      Monitoring Data

3.2      Monitoring Exceedances

3.2.1         1-hour TSP Monitoring

3.2.2         24-hour TSP Monitoring

3.2.3         Construction Noise Monitoring

3.2.4         Landscape and Visual Monitoring

4       Waste Management

4.1      Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095)

5       Environmental Non-conformance

6       Comments, Recommendations and Conclusion

6.1      Comments

6.2      Recommendations

6.3      Conclusion

Figure 1      Site Layout Plan and Monitoring Stations

Appendices

A.      Project Organisation

B.      Construction Programme

C.      Environmental Mitigation Measures ¡V Implementation Status

D.      Meteorological Data Extracted from Hong Kong Observatory

E.      Graphical Plots of the Monitoring Results

F.      Waste Flow table

G.      Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions

 

  


Executive summary

This Quarterly EM&A Report presents the monitoring works conducted at Zones 2A, 2B & 2C from 01 February 2026 to 30 April 2026.

Exceedance of Action and Limit Levels

There was no breach of Action or Limit Levels for Air Quality (1-hour TSP and 24-hour TSP) and Noise in this reporting quarter.

Implementation of Mitigation Measures

Construction phase weekly site inspections were carried out to confirm the implementation measures undertaken by the Contractors in the reporting quarter. The status of implementation of mitigation measures during the reporting quarter is shown in Appendix C.

Landscape and visual impact inspections were conducted as part of the above-mentioned weekly site inspections during the reporting quarter. No adverse comment on landscape and visual aspects were made during these inspections.

Record of Complaints

2 environmental complaint was received during the reporting quarter.

Record of Notifications of Summons and Successful Prosecutions

No notifications of summons and successful prosecutions were recorded in the reporting quarter.

 

 

 

1        Introduction

1.1             Background

Apex Testing & Certification Limited (Apex) was commissioned to undertake the Environmental Team (ET) services (including environmental monitoring and audit (EM&A)) for the construction activities in Zone 2A, consisting of Foundation, Excavation and Lateral Support Works for Integrated Basement and Underground Road (Contract No.: GW/2020/05/073) ; Zone 2B & 2C consisting of Piling Works for Integrated Basement and Underground Road (Contract No.: CC/2020/2B/088); and Zones 2A, 2B & 2C consisting of Excavation and Lateral Support Works (Stages 1 & 2) for The Integrated Basement and Underground Road (Contract No.: CC/2023/2B/095) at WKCD. The construction works and EM&A programme for Zone 2A (Contract No.: GW/2020/05/073) was commenced on 03 October 2020 and handed over on 31 March 2023; while the construction works and EM&A programme for Zone 2B & 2C (Contract No.: CC/2020/2B/088) was commenced on 30 September 2021 and handed over on 05 July 2024. The construction works and EM&A programme for Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) was commenced on 05 July 2024.

The overall works for the WKCD fall under two separate categories of Designated Project (DP) of the Environmental Impact Assessment Ordinance (EIAO), namely an ¡§engineering feasibility study of urban development projects with a study area covering more than 20 ha or involving a total population of more than 100 000¡¨ (Item 1 of Schedule 3) and ¡§an underpass more than 100m in length under the built areas¡¨ (Item A.9, Part I, Schedule 2). An Environmental Permit No. EP-453/2013/B (EP) was issued with respect to the ¡§Underpass Road and Austin Road Flyover Serving the West Kowloon Cultural District¡¨ which specifically includes the abovementioned category of DP under Item A.9, Part I, Schedule 2 of the EIAO. The captioned projects include part of the abovementioned underpass road located within the site boundary falls under this same category.

The purpose of the development in Zones 2A, 2B & 2C is to reserve for Integrated Basement (IB) and Underground Road (UR). The Zone 2A (Contract No.: GW/2020/05/073) construction activities involve the foundation, excavation and lateral support (ELS) works, road works, drainage diversion works, and temporary car parking. The Zone 2B & 2C (Contract No.: CC/2020/2B/088) construction activities involve the piling works. The Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) construction activities involve the excavation and lateral support works.

The Quarterly EM&A Report is prepared in accordance with the Clause 3.4 of the Environmental Permit No. EP-453/2013/B. This Quarterly EM&A Report presents the monitoring works Zones 2A, 2B & 2C from 01 February 2026 to 30 April 2026. The purpose of this report is to summarise the findings in the EM&A of the project over the reporting period.

1.2             Project Organisation

The organisation chart and lines of communication with respect to the on-site environmental management structure together with the contact information of the key personnel are shown in Appendix A.

1.3             Environmental Status in the Reporting Period

During the reporting period, construction works at Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) undertaken include:

¡´    Pipe Pile and King Post Works

¡´    Jet Grouting Works

¡´    Double Deck Hoarding Works

¡´    Temporary Steel Platform

¡´    ELS Work

¡´    Operation of Barging Point

¡´    Hoarding Work

 

The Construction Works Programme of the Project is provided in Appendix B. A layout plan of the Project is provided in Figure 1.

2        Summary of EM&A Requirements and Mitigation Measures

2.1             Monitoring Requirements

In accordance with the EM&A Manual, environmental parameters including air quality, noise, landscape and visual have been monitored. The specific parameters, monitoring frequency and the respective Action and Limit Levels are given in Table 2.1. Locations of the monitoring stations are provided in Figure 1.

Table 2.1:         Summary of Impact EM&A Requirements

Parameters

Descriptions

Locations

Frequencies

Action Level

Limit Level

Air Quality

24-Hour TSP

AM3 - The Victoria Towers Tower 1

At least once every 6 days

152.4 £gg/m3

260 £gg/m3

1-Hour TSP

AM3 - The Victoria Towers Tower 1

At least 3 times every 6 days

280.4 £gg/m3

500 £gg/m3

24-Hour TSP

AM4 - Canton Road Government Primary School

At least once every 6 days

152.6 £gg/m3

260 £gg/m3

1-Hour TSP

AM4 - Canton Road Government Primary School

At least 3 times every 6 days

278.5 £gg/m3

500 £gg/m3

24-Hour TSP

AM5 - Topside Developments at West Kowloon Terminus Site

At least once every 6 days

141.1 £gg/m3

260 £gg/m3

1-Hour TSP

AM5 - Topside Developments at West Kowloon Terminus Site

At least 3 times every 6 days

275.4 £gg/m3

500 £gg/m3

Noise

Leq, 30 minutes

NM2 - The Arch, Sun Tower

Weekly

When one documented complaint is received from any one of the sensitive receivers

75 dB(A)

Leq, 30 minutes

NM3 - The Victoria Towers Tower 1

Weekly

When one documented complaint is received from any one of the sensitive receivers

75 dB(A)

Leq, 30 minutes

NM4 - Canton Road Government Primary School

Weekly

When one documented complaint is received from any one of the sensitive receivers

70/65 dB(A)^

Leq, 30 minutes

NM5 -Development next to Austin Station

Weekly

When one documented complaint is received from any one of the sensitive receivers

75 dB(A)

Landscape & Visual

Monitor implementation of proposed mitigation measures during the construction stage

As described in Table 9.1 and 9.2 of the EM&A Manual

Bi-weekly

N/A

N/A

Note:

^70 dB(A) for schools and 65 dB(A) during school examination periods.

The EM&A programme for the Project require 5 air monitoring stations and 5 noise quality monitoring stations located closest to the Project area. With regard to the monitoring activities at M+ Museum and the Lyric Complex, three monitoring stations had been considered, including AM1, AM2 for air monitoring, and NM1 for noise monitoring. In the context of the construction activities in Zone 2A and Zone 2B & 2C, all other monitoring locations including AM3, AM4, and AM5 for air monitoring; and NM2, NM3, NM4 and NM5 for noise monitoring, have been taken into account. However, access to all these originally designated monitoring stations was declined. Therefore, alternative monitoring stations was identified and proposed. 

With regard to air monitoring, alternative monitoring locations (AM3A, AM4A, and AM5A) were identified at ground floor at the Northeast corner of West Kowloon Station¡¦s station box, at ground floor at the Southeast corner of West Kowloon Station¡¦s station box, and at ground floor at the North of West Kowloon Station¡¦s station box respectively. AM3A, AM4A, and AM5A were set in same direction to the area of major construction site activities in Zone 2A. These alternative air monitoring locations (AM3A, AM4A, and AM5A) were approved by EPD on 29 September 2020. 

For noise monitoring, alternative noise monitoring location (NM2A) was identified at the ground floor in front of The Arch - Sun Tower, which is at the same location as stated in the EM&A Manual for consistency. This alternative noise monitoring location was approved by EPD on 29 September 2020. Other alternative noise monitoring locations (NM3A, NM4A, and NM5A) were identified at the ground floor in front of the Xiqu Centre, at the ground floor next to Tsim Sha Tsui Fire Station, and at the Pedestrian road (ground floor) outside West Kowloon Station respectively. NM3A, NM4A and NM5A were set closer to the construction site boundary with more direct line sight to the major site activities and higher exposure to the construction noise with no disturbance to the premises¡¦ occupants during noise monitoring activities. These alternative noise monitoring locations (NM3A, NM4A, and NM5A) were approved by EPD on 29 September 2020.

Therefore, 3 air quality monitoring stations and 4 noise impact monitoring station were confirmed for the impact monitoring for construction activities in Zone 2A and Zone 2B & 2C.

2.2             Environmental Mitigation Measures

Environmental mitigation measures have been recommended in the EM&A Manual. Summary of implementation status of the environmental mitigation measures is provided in Appendix C.

 

 

 

3        Summary of EM&A Results

3.1             Monitoring Data

In accordance with the EM&A Manual, impact monitoring has been conducted in the reporting quarter. Meteorological data for the reporting quarter have been extracted from Hong Kong Observatory and presented in Appendix D. Monitoring data with graphical presentation for the reporting quarter are shown in Appendix E. A summary on the monitoring results is presented in Table 3.1.

Table 3.1:         Summary of Monitoring Data

Parameter

Monitoring Location

Minimum

Maximum

Average

Air Quality

 

 

 

 

1 hour TSP

AM3A

31

56

44

1 hour TSP

AM4A

32

59

44

1 hour TSP

AM5A

31

58

44

24 hour TSP

AM3A

31

52

40

24 hour TSP

AM4A

31

54

40

24 hour TSP

AM5A

33

52

41

Construction Noise

 

 

 

 

Leq(30min)

NM2A

63

63

63

Leq(30min)

NM3A

60

61

61

Leq(30min)

NM4A

58

59

58

Leq(30min)

NM5A

63

64

64

3.2             Monitoring Exceedances

Summary of the exceedances in the reporting quarter is tabulated in Table 3.2.

Table 3.2:         Summary of Exceedances

Monitoring Station

Parameter

No. of Exceedance

Action Taken

Action Level

Limit Level

Air Quality

 

 

 

 

AM3A

1 hour TSP

0

0

N/A

24 hour TSP

0

0

N/A

AM4A

1 hour TSP

0

0

N/A

24 hour TSP

0

0

N/A

AM5A

1 hour TSP

0

0

N/A

24 hour TSP

0

0

N/A

Construction Noise

 

 

 

 

NM2A

Leq(30min)

0

0

N/A

NM3A

Leq(30min)

0

0

N/A

NM4A

Leq(30min)

0

0

N/A

NM5A

Leq(30min)

0

0

N/A

3.2.1         1-hour TSP Monitoring

All 1-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of 1-hour TSP for Air Quality was recorded.

3.2.2         24-hour TSP Monitoring

All 24-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of 24-hour TSP for Air Quality was recorded.

3.2.3         Construction Noise Monitoring

All construction noise monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of Noise was recorded in the reporting quarter.

3.2.4         Landscape and Visual Monitoring

All landscape and visual impact inspections were conducted as scheduled in the reporting quarter. No adverse comment on landscape and visual aspects were recorded.

 

 

 

4        Waste Management

4.1        Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095)

As advised by the Zones 2A, 2B & 2C Contractor, 48852.22 tonne and 0.0 tonne of inert C&D material were disposed of as public fill to Tseung Kwan O Area 137 and Tuen Mun Area 38 in the reporting quarter, while 160.05 tonne of general refuse were disposed of at SENT and WENT landfill. 0.0 tonne of metals, 0.0 tonne of paper/cardboard packaging, 0.0 tonne of plastics and 0.0 tonne of timber was collected by recycling contractors in the reporting quarter. 0.0 tonne of inert C&D material were reused on site. 0.0 tonne of inert C&D material was imported for reuse at site and 61209.41 tonne of inert C&D material were reused in other projects. 277.72 tonne of inert C&D material was disposed to sorting facility and 1.4 tonne of chemical waste was collected by licensed contractors in the reporting quarter.

The actual amounts of different types of waste generated by the activities of construction works at Zones 2A, 2B & 2C in the reporting quarter are shown in Appendix F.

 

 

 

5        Environmental Non-conformance

There was no breach of Action or Limit Levels for Air Quality (1-hour TSP and 24-hour TSP) and Noise in the reporting quarter.

Two complaints were received in the reporting quarter. No notifications of summons and successful prosecutions were received in the reporting quarter.

On 2 March 2026, the WKCDA referred a complaint case received via hotline on 1 Mar 2026 regarding noise disturbance caused by ongoing construction work near Artist Square Bridge from 9 a.m. on 1 March 2026. The Complaint enquired about the duration of construction work, whether a permit has been obtained from Environmental Protection Department as the construction activity is carrying out on Sunday, whether it will continue every Sunday, and the contact point of the construction site. Further to the complaint email received on 02 March 2026, investigation was carried out at WKCD Zone 2A, 2B & 2C site. According to the message from the complaint, noise nuisance from construction site near Artist Square Bridge was observed starting from 9am on 01 March 2026. During the inspection after received the enquiry, it was found that cleansing work at grouting station in Zone 2C near Zone 3 conducted on 1 Mar 2026. After reviewing the concerned site activities, the cleansing works was originally meant to be conducted with water jet and brushes only, however, the workers found certain valve or joint stuck and they tried to overcome, and so caused the noise nuisance.

To minimize the environmental impacts to the surrounding, number of mitigation measures were implemented. After notification of the complaint, immediate actions have been taken on site to improve the noise control and mitigation measures. In addition, as preventive measure, machinery shall be rinsed immediately after use to avoid the components got stuck, and the noisy cleansing work at grout station is now prohibited to be conducted in restricted hours. According to the noise monitoring results on 1 March 2026, the measured noise levels (dB(A)) were below the limit level of 70dB(A). It was concluded that the concerned environmental impact might be due to the site works, especially the cleansing at grout station in the site. And under current site planning procedures, the works beyond normal working hours were planned to be conducted occasionally throughout the project under effective construction noise permit (CNP). However, as to minimize the impact to the surrounding, the noisy cleansing work at grout station would be prohibited in restricted hours. A direct contact to our site agent, Mr. Gary Wong, is welcome to any further queries. On-site mitigation measures have already been implemented and maintained on site and prompt actions have been taken. The contractor will keep maintain good practice on site, and strengthen the implementation of mitigation measures to reduce impacts to the nearby neighbors.

On 17 April 2026 (Friday), the site received a complaint from the Harbourside Owners Committee through WKCDA regarding dust pollution arising from ongoing construction activities within the West Kowloon Cultural District area. The Committee has expressed doubts in the proper operation of the dust suppression measures as three mist cannons were observed to be idled on-site and their further concerns about the negative impact this dust is having on the residents' living environment and health. Further to the complaint email received on 17 April 2026, investigation was carried out at WKCD Zone 2A, 2B & 2C site. According to the message from the complaint, the construction dust has significantly degraded the living environment and raised serious public health concerns. Complaint also expressed their doubts in the proper operation of the dust suppression measures as three mist cannons were observed to be idled on-site. During the inspection, the condition of the dust suppression measures was checked. On-site dust suppression measures were found in place and functioning. According to the site record, the concerned mist cannons were temporarily disconnected on 27 Mar 26 as to facilitate the relocation for setup of the new C&D material stockpiling area. The mist cannons have resumed operation on 17 Apr 26. During the interim period, manual water spaying by worker was conducted as an intermediate dust suppression measures.

As advised by the Contractor, the major construction works undertaken in March 2026 were Excavation and Installation of ELS & Erection of Temporary Steel Platform. To minimize the environmental impacts to the surrounding, number of mitigation measures were implemented. During ET¡¦s regular site inspections on 4, 11, 18, 25, 31 March 2026 and 8, 15 April 2026, three areas for attention regarding dust suppression were noted: full coverage of dusty material stockpiles, timely and increased watering of access road, and targeted and sufficient watering prior to soil transport. During the follow-up visit, it was observed that the contractor had strengthened the relevant dust suppression measures. After notification of the complaint, immediate actions have been taken on site to improve the dust control for vehicles. A detail dust control plan has been updated. The operation frequency for all dust suppression measure is now regulated at a minimum of once per hour. The actual frequency will be adjusted dynamically based on prevailing weather conditions. Furthermore, a supervision staff would monitor the site conditions to ensure the ground surface and material stockpiles maintain adequate moisture levels at all times. According to the recent dust monitoring results in March & April 2026, the measured dust levels (µg/m3) were below the action levels at each monitoring point and the limit level of 500µg/m3. It was concluded that the concerned environmental impact might be due to the construction works and transportation in the site. The mist cannons were temporarily taken offline on 27 Mar 2026 for relocation. During this period, manual water spraying was used as an interim dust suppression measure, adjusted based on moisture content. On-site mitigation measures have already been implemented and maintained and prompt actions have been taken. The contractor shall keep maintain good practice on site, and strengthen the implementation of mitigation measures to reduce impacts to the nearby neighbours.

 

The cumulative statistics on complaints, notifications of summons and successful prosecutions were provided in Appendix G.

 

 

 

6        Comments, Recommendations and Conclusion

6.1             Comments

Based on the observations made during site audits and landscape inspections, and construction dust and noise monitoring results, no non-compliances and exceedances of air quality and construction noise were recorded in the reporting quarter.

6.2             Recommendations

Reviewing the implementation of the recommended mitigation measures in the EM&A Manual, it was observed that they were effective and efficient in controlling the potential impacts due to construction of the project during the reporting period. Review of the effectiveness and efficiency of the EM&A programme will continue, and recommendations will be provided to remediate any potential impacts due to the project and to improve the EM&A programme if deficiencies of the existing EM&A programme are identified.

6.3             Conclusion

The EM&A programme as recommended in the EM&A Manual has been undertaken. The construction works and EM&A programme for Zone 2A (Contract No.: GW/2020/05/073) was commenced on 03 October 2020 and handed over on 31 March 2023; while the construction works and EM&A programme for Zone 2B & 2C (Contract No.: CC/2020/2B/088) was commenced on 30 September 2021 and handed over on 05 July 2024. The construction works and EM&A programme for Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) was commenced on 05 July 2024.

Monitoring of air quality and noise with respect to the Project is underway. In particular, the 1-hour TSP, 24-hour TSP and noise level (as Leq, 30 minutes) under monitoring have been checked against established Action and Limit Levels. There was no breach of Action or Limit Levels for Air Quality (1-hour TSP and 24-hour TSP) and Noise in this reporting quarter.

Two complaints were received in the reporting quarter. No notifications of summons and successful prosecutions were received during the reporting quarter.

Weekly construction phase site inspections and bi-weekly landscape and visual impact inspections were conducted during the reporting quarter as required. It was observed that the Contractor had implemented all possible and feasible mitigation measures to mitigate the potential environmental impacts during construction phase works.