Contents
1.3 Environmental
Status in the Reporting Period
2 Summary of EM&A Requirements and
Mitigation Measures
2.2 Environmental
Mitigation Measures
3.2.3 Construction
Noise Monitoring
3.2.4 Landscape
and Visual Monitoring
4.1 Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095)
5 Environmental Non-conformance
6 Comments, Recommendations and Conclusion
Figure 1 Site Layout Plan and Monitoring Stations
C. Environmental Mitigation
Measures – Implementation Status
D. Meteorological Data Extracted
from Hong Kong Observatory
E. Graphical Plots of the
Monitoring Results
G. Cumulative Statistics on
Complaints, Notifications of Summons and Successful Prosecutions
This Quarterly EM&A Report
presents the monitoring works conducted at Zones 2A, 2B & 2C from 01 August 2025 to 30 October 2025. The construction works and
EM&A programme for Zone 2A (Contract No.: GW/2020/05/073) was commenced on
03 October 2020 and handed over on 31 March 2023; while the construction works
and EM&A programme for Zone 2B & 2C (Contract No.: CC/2020/2B/088) was
commenced on 30 September 2021 and handed over on 05 July 2024. The
construction works and EM&A programme for Zones 2A, 2B & 2C (Contract
No.: CC/2023/2B/095) was commenced on 05 July 2024.
The impact stage EM&A
programme for the Project includes air quality, noise, water quality, waste,
landscape and visual monitoring. The recommended environmental mitigation
measures were implemented on site and regular inspections were carried out to
ensure that the environmental conditions are acceptable.
Exceedance of Action and Limit Levels
There was no breach of Action or Limit Levels for Air Quality (1-hour
TSP and 24-hour TSP) and Noise in this reporting quarter.
Implementation of Mitigation Measures
Construction phase weekly site
inspections were carried out to confirm the implementation measures undertaken
by the Contractors in the reporting quarter. The status of implementation of
mitigation measures during the reporting quarter is shown in Appendix C.
Landscape and visual impact inspections were conducted as part of the above-mentioned weekly site inspections during the reporting quarter. No adverse comment on landscape and visual aspects were made during these inspections.
Record of
Complaints
1 environmental complaint was received during the reporting quarter.
Record of Notifications of Summons and Successful Prosecutions
No notifications of summons and successful prosecutions were recorded in the reporting quarter.
Apex Testing & Certification Limited (Apex) was commissioned to
undertake the Environmental Team (ET) services (including environmental
monitoring and audit (EM&A)) for the construction activities in Zone 2A,
consisting of Foundation, Excavation and Lateral Support Works for Integrated
Basement and Underground Road (Contract No.: GW/2020/05/073) ; Zone 2B
& 2C consisting of Piling Works for Integrated Basement and Underground
Road (Contract No.: CC/2020/2B/088); and Zones 2A, 2B & 2C consisting of
Excavation and Lateral Support Works (Stages 1 & 2) for The Integrated
Basement and Underground Road (Contract No.: CC/2023/2B/095) at WKCD. The
construction works and EM&A programme for Zone 2A (Contract No.:
GW/2020/05/073) was commenced on 03 October 2020 and handed over on 31 March
2023; while the construction works and EM&A programme for Zone 2B & 2C
(Contract No.: CC/2020/2B/088) was commenced on 30 September 2021 and handed
over on 05 July 2024. The construction works and EM&A programme for Zones
2A, 2B & 2C (Contract No.: CC/2023/2B/095) was commenced on 05 July 2024.
The overall works for the
WKCD fall under two separate categories of Designated Project (DP) of the
Environmental Impact Assessment Ordinance (EIAO), namely an “engineering
feasibility study of urban development projects with a study area covering more
than 20 ha or involving a total population of more than 100 000” (Item 1 of
Schedule 3) and “an underpass more than 100m in length under the built areas”
(Item A.9, Part I, Schedule 2). An Environmental Permit No. EP-453/2013/B (EP) was issued with respect to the “Underpass Road and Austin Road
Flyover Serving the West Kowloon Cultural District” which specifically includes
the abovementioned category of DP under Item A.9, Part I, Schedule 2 of the
EIAO. The captioned projects include part of the abovementioned underpass road
located within the site boundary falls under this same category.
The purpose of the development in Zones 2A, 2B & 2C is to reserve for
Integrated Basement (IB) and Underground Road (UR). The Zone 2A (Contract No.: GW/2020/05/073)
construction activities involve the foundation, excavation and lateral support
(ELS) works, road works, drainage diversion works, and temporary car parking.
The Zone 2B & 2C (Contract No.: CC/2020/2B/088) construction activities involve the
piling works. The Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) construction activities involve the excavation and lateral support works.
The Quarterly EM&A Report is
prepared in accordance with the Clause 3.4 of the Environmental Permit No.
EP-453/2013/B. This Quarterly EM&A Report presents the monitoring works Zones 2A, 2B & 2C from 01 August 2025 to 30 October 2025. The purpose of this report is to summarise
the findings in the EM&A of the project over the reporting period.
During the reporting period, construction works
at Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) undertaken include:
● Bored Pile, Pipe Pile and King Post Works
● Jet Grouting Works
● Double Deck Hoarding Works
● Temporary Steel Platform
● ELS installation
The Construction Works Programme of the
Project is provided in Appendix B. A layout plan of the Project is provided in Figure 1.
In accordance with the EM&A Manual,
environmental parameters including air quality, noise, landscape and visual have
been monitored. The specific parameters, monitoring frequency and the
respective Action and Limit Levels are given in Table 2.1. Locations of the monitoring stations are provided in Figure 1.
Table 2.1: Summary of Impact EM&A Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
Action
Level |
Limit
Level |
|
Air Quality |
24-Hour
TSP |
AM3
- The Victoria Towers Tower 1 |
At
least once every 6 days |
152.4
μg/m3 |
260
μg/m3 |
|
1-Hour
TSP |
AM3
- The Victoria Towers Tower 1 |
At
least 3 times every 6 days |
280.4
μg/m3 |
500
μg/m3 |
|
|
24-Hour TSP |
AM4 - Canton Road Government Primary
School |
At
least once every 6 days |
152.6 μg/m3 |
260
μg/m3 |
|
|
1-Hour TSP |
AM4 - Canton Road Government Primary
School |
At
least 3 times every 6 days |
278.5 μg/m3 |
500
μg/m3 |
|
|
24-Hour TSP |
AM5 - Topside Developments at West Kowloon
Terminus Site |
At
least once every 6 days |
141.1
μg/m3 |
260
μg/m3 |
|
|
1-Hour TSP |
AM5 - Topside Developments at West Kowloon
Terminus Site |
At
least 3 times every 6 days |
275.4
μg/m3 |
500
μg/m3 |
|
|
Noise |
Leq,
30 minutes |
NM2
- The Arch, Sun Tower |
Weekly |
When
one documented complaint is received from any one of the sensitive receivers |
75
dB(A) |
|
Leq,
30 minutes |
NM3
- The Victoria Towers Tower 1 |
Weekly |
When
one documented complaint is received from any one of the sensitive receivers |
75
dB(A) |
|
|
Leq,
30 minutes |
NM4
- Canton Road Government Primary School |
Weekly |
When
one documented complaint is received from any one of the sensitive receivers |
70/65
dB(A)^ |
|
|
Leq,
30 minutes |
NM5
-Development next to Austin Station |
Weekly |
When
one documented complaint is received from any one of the sensitive receivers |
75
dB(A) |
|
|
Landscape & Visual |
Monitor
implementation of proposed mitigation measures during the construction stage |
As
described in Table 9.1 and 9.2 of the EM&A Manual |
Bi-weekly |
N/A |
N/A |
Note:
^70 dB(A) for schools
and 65 dB(A) during school examination periods.
The EM&A programme
for the Project require 5 air monitoring stations and 5 noise quality
monitoring stations located closest to the Project area. With regard to the
monitoring activities at M+ Museum and the Lyric Complex, three monitoring
stations had been considered, including AM1, AM2 for air monitoring, and NM1
for noise monitoring. In the context of the construction activities in Zone 2A
and Zone 2B & 2C, all other monitoring locations including AM3, AM4, and
AM5 for air monitoring; and NM2, NM3, NM4 and NM5 for noise monitoring, have
been taken into account. However, access to all these originally designated
monitoring stations was declined. Therefore, alternative monitoring stations
was identified and proposed.
With regard to air monitoring, alternative
monitoring locations (AM3A, AM4A, and AM5A) were identified at ground floor at
the Northeast corner of West Kowloon Station’s station box, at ground floor at
the Southeast corner of West Kowloon Station’s station box, and at ground floor
at the North of West Kowloon Station’s station box respectively. AM3A, AM4A,
and AM5A were set in same direction to the area of major construction site
activities in Zone 2A. These alternative air monitoring locations (AM3A, AM4A, and
AM5A) were approved by EPD on 29 September 2020.
For noise monitoring, alternative noise monitoring
location (NM2A) was identified at the ground floor in front of The Arch - Sun
Tower, which is at the same location as stated in the EM&A Manual for
consistency. This alternative noise monitoring location was approved by EPD on
29 September 2020. Other alternative noise monitoring locations (NM3A, NM4A,
and NM5A) were identified at the ground floor in front of the Xiqu Centre, at the ground floor next to Tsim Sha Tsui Fire
Station, and at the Pedestrian road (ground floor) outside West Kowloon Station
respectively. NM3A, NM4A and NM5A were set closer to the construction site
boundary with more direct line sight to the major site activities and higher
exposure to the construction noise with no disturbance to the premises’
occupants during noise monitoring activities. These alternative noise
monitoring locations (NM3A, NM4A, and NM5A) were approved by EPD on 29
September 2020.
Therefore, 3 air quality monitoring stations and 4
noise impact monitoring station were confirmed for the impact monitoring for
construction activities in Zone 2A and Zone 2B & 2C.
Environmental mitigation measures have been recommended in the EM&A Manual. Summary of implementation status of the environmental mitigation measures is provided in Appendix C.
In accordance with the EM&A Manual, impact
monitoring has been conducted in the reporting quarter. Meteorological data for
the reporting quarter have been extracted from Hong Kong Observatory and
presented in Appendix D. Monitoring
data with graphical presentation for the reporting quarter are shown in Appendix E. A summary on the monitoring
results is presented in Table 3.1.
Table 3.1: Summary
of Monitoring Data
|
Parameter |
Monitoring Location |
Minimum |
Maximum |
Average |
|
Air Quality |
|
|
|
|
|
1 hour TSP |
AM3A |
31 |
51 |
41 |
|
1 hour TSP |
AM4A |
31 |
50 |
40 |
|
1 hour TSP |
AM5A |
31 |
50 |
41 |
|
24 hour TSP |
AM3A |
29 |
46 |
37 |
|
24 hour TSP |
AM4A |
31 |
46 |
37 |
|
24 hour TSP |
AM5A |
32 |
46 |
39 |
|
Construction Noise |
|
|
|
|
|
Leq(30min) |
NM2A |
62 |
63 |
63 |
|
Leq(30min) |
NM3A |
60 |
61 |
61 |
|
Leq(30min) |
NM4A |
58 |
59 |
58 |
|
Leq(30min) |
NM5A |
63 |
64 |
64 |
Summary of the exceedances in the reporting quarter is tabulated in Table 3.2.
Table 3.2: Summary
of Exceedances
|
Monitoring
Station |
Parameter |
No. of Exceedance |
Action Taken |
|
|
Action
Level |
Limit
Level |
|||
|
Air
Quality |
|
|
|
|
|
AM3A |
1 hour TSP |
0 |
0 |
N/A |
|
24 hour TSP |
0 |
0 |
N/A |
|
|
AM4A |
1 hour TSP |
0 |
0 |
N/A |
|
24 hour TSP |
0 |
0 |
N/A |
|
|
AM5A |
1 hour TSP |
0 |
0 |
N/A |
|
24 hour TSP |
0 |
0 |
N/A |
|
|
Construction
Noise |
|
|
|
|
|
NM2A |
Leq(30min) |
0 |
0 |
N/A |
|
NM3A |
Leq(30min) |
0 |
0 |
N/A |
|
NM4A |
Leq(30min) |
0 |
0 |
N/A |
|
NM5A |
Leq(30min) |
0 |
0 |
N/A |
All 1-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of 1-hour TSP for Air Quality was recorded.
All 24-hour TSP monitoring was conducted as scheduled in the reporting quarter. No Action/ Limit Level exceedance of 24-hour TSP for Air Quality was recorded.
All construction noise monitoring was
conducted as scheduled in the reporting quarter. No
Action/ Limit Level exceedance of Noise was recorded in the
reporting quarter.
All landscape and visual impact inspections were conducted as scheduled in the reporting quarter. No adverse comment on landscape and visual aspects were recorded.
As
advised by the Zones 2A, 2B & 2C Contractor, 39635.06 tonne and 160.11 tonne of
inert C&D material were disposed of as public fill to Tseung Kwan O
Area 137 and Tuen Mun Area 38 in the reporting quarter, while 164.37 tonne of
general refuse were disposed of at SENT landfill. 46.33 tonne of metals, 0.0 tonne of paper/cardboard
packaging, 0.0 tonne of plastics and 0.0 tonne of timber was collected by
recycling contractors in the reporting quarter. 0.00
tonne of inert C&D material were reused on site. 0.0 tonne of inert C&D
material was imported for reuse at site and 17863.97 tonne of
inert C&D material were reused in other projects. 0.0 tonne of inert C&D material was disposed
to sorting facility and 0.0 tonne of chemical waste was collected by
licensed contractors in the reporting
quarter.
The actual amounts of different
types of waste generated by the activities of construction works at Zones 2A, 2B & 2C in the reporting
quarter are shown in Appendix F.
One complaint was received in the reporting quarter. No notifications of summons and successful prosecutions were received in the reporting quarter.
On 20 October 2025 (Monday), WKCDA received a complaint from Culture,
Sports and Tourism Bureau (CSTB) regarding dust and dirt near WKCD construction
site. The complaint was regarding dissatisfaction to construction works near
Austin Road West causing serious dust and dirt in the air and on the road. The
complaint provided photos of dust and dirt along the road. Further to the complaint email received on 21
October 2025, investigation was carried out at WKCD Zone 2A, 2B & 2C site.
According to the message from the complaint, the carriageway became dusty while
the vehicle pass by and dirt was discovered on the
carriageway. During the inspection, the
condition of the site entrance was checked. No significant dirt or muddy track
was observed from the site entrance. In addition, the condition of the site
entrance was also checked in daily inspection on 18 and 20 October 2025. In the context of Environmental Monitoring and Audit (EM&A) for
WKCD Zone 2A, 2B & 2C site, the representative dust monitoring location nearest
is AM5A. Dust monitoring at AM5A (North of West Kowloon Station’s station box,
G/F) monitoring station had been conducted under the EM&A requirement.
According to the recent dust monitoring results in October 2025, the measured
dust level (µg/m3) was below the action level of 275.4µg/m3 and the limit level
of 500µg/m3. The concerned condition might
not be directly related to the site. However, the heavy transportation from
site might still contribute to some of the dirt and dust on the carriageway.
To
minimize the environmental impacts to the surrounding, number of mitigation
measures were implemented, including wheel washing for all vehicle before leaving site, monitoring
and control of vehicle by security guard, and checking of clousre
of dump truck skip cover. After notification of the complaint, immediate actions have been taken
on site to improve the dust control for vehicles. Ad-hoc training on wheel washing and site entrance
management was provided to the frontline staff deployed at site entrance. It was concluded that the
transportation from site might partially contributed to the concerned
environmental impact. On-site mitigation measures have already been implemented
and maintained on site and prompt actions have been taken. We will keep
maintain good practice on site, and strengthen the implementation of mitigation
measures to reduce impacts to the nearby neighbors.
The cumulative statistics on complaints, notifications of summons and successful prosecutions were provided in Appendix G.
Based on the observations made during site audits and landscape inspections, and construction dust and noise monitoring results, no non-compliances and exceedances of air quality and construction noise were recorded in the reporting quarter.
Reviewing the implementation of the recommended mitigation measures in the EM&A Manual, it was observed that they were effective and efficient in controlling the potential impacts due to construction of the project during the reporting period. Review of the effectiveness and efficiency of the EM&A programme will continue, and recommendations will be provided to remediate any potential impacts due to the project and to improve the EM&A programme if deficiencies of the existing EM&A programme are identified.
The EM&A programme as recommended in the EM&A Manual has
been undertaken. The construction works and EM&A programme for Zone 2A
(Contract No.: GW/2020/05/073) was commenced on 03 October 2020 and handed over
on 31 March 2023; while the construction works and EM&A programme for Zone
2B & 2C (Contract No.: CC/2020/2B/088) was commenced on 30 September 2021
and handed over on 05 July 2024. The construction works and EM&A programme
for Zones 2A, 2B & 2C (Contract No.: CC/2023/2B/095) was commenced on 05
July 2024.
Monitoring of air quality and noise with respect to the Project is
underway. In particular, the 1-hour TSP, 24-hour TSP and noise level (as Leq, 30 minutes) under monitoring have been checked against
established Action and Limit Levels. There was no breach of Action or Limit Levels
for Air Quality (1-hour TSP and 24-hour TSP) and Noise in this reporting
quarter.
One complaint was received in the reporting quarter. No notifications of summons and successful prosecutions were received
during the reporting quarter.
Weekly
construction phase site inspections and bi-weekly landscape and visual impact
inspections were conducted during the reporting quarter as required. It was
observed that the Contractor had implemented all possible and feasible
mitigation measures to mitigate the potential environmental impacts during
construction phase works.